[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-789-50":3},{"library":4,"page":9,"limit":9,"total":10,"questions":11,"related":595},{"id":5,"name":6,"category":7,"favorite":8},789,"二建建设工程施工管理","建筑工程",0,50,2973,[12,33,45,57,69,81,93,105,116,128,140,152,164,176,188,200,212,224,236,248,260,272,281,293,305,317,329,341,351,359,371,380,392,403,414,423,435,444,456,465,477,489,501,513,524,536,548,559,571,583],{"id":13,"libraryId":5,"type":14,"typeLabel":15,"stem":16,"options":17,"answer":26,"analysis":32},1119533,1,"单选题","“三同时”制度是指新建、改建、扩建工程的安全生产设施必须与主体工程( )。",[18,22,25,29],{"key":19,"text":20,"correct":21},"A","同时设计、同时规划、同时施工",false,{"key":23,"text":24,"correct":21},"B","同时报建、同时设计、同时施工",{"key":26,"text":27,"correct":28},"C","同时设计、同时施工、同时投入生产和使用",true,{"key":30,"text":31,"correct":21},"D","同时报建、同时施工、同时投入生产和使用","",{"id":34,"libraryId":5,"type":14,"typeLabel":15,"stem":35,"options":36,"answer":23,"analysis":32},1119534,"按照国家标准《生产过程危险和有害因素分类与代码》GB\u002FT13861-2009，危险源可以分为人的因素、物的因素、环境因素和( )。",[37,39,41,43],{"key":19,"text":38,"correct":21},"设备因素",{"key":23,"text":40,"correct":28},"管理因素",{"key":26,"text":42,"correct":21},"材料因素",{"key":30,"text":44,"correct":21},"方法因素",{"id":46,"libraryId":5,"type":14,"typeLabel":15,"stem":47,"options":48,"answer":19,"analysis":32},1119535,"根据危险源在事故发生发展中的作用，把危险源分为两大类，即第一类危险源和第二类危险源。下列危险源不属于第二类危险源特征的是()。",[49,51,53,55],{"key":19,"text":50,"correct":28},"能量或危险物质的量",{"key":23,"text":52,"correct":21},"管理缺陷",{"key":26,"text":54,"correct":21},"设备故障或缺陷",{"key":30,"text":56,"correct":21},"人为失误",{"id":58,"libraryId":5,"type":14,"typeLabel":15,"stem":59,"options":60,"answer":30,"analysis":32},1119536,"施工搅拌站的污水，水磨石的污水等须经排水沟和（）",[61,63,65,67],{"key":19,"text":62,"correct":21},"根据施工方便就近排放",{"key":23,"text":64,"correct":21},"直接排入市政排水管网或河流",{"key":26,"text":66,"correct":21},"直接排出场外",{"key":30,"text":68,"correct":28},"通过现场沉淀池后排入城市污水管道或河流",{"id":70,"libraryId":5,"type":14,"typeLabel":15,"stem":71,"options":72,"answer":23,"analysis":32},1119537,"根据我国《建筑施工场界环境噪声排放标准》(GB12523-2011)规定，建筑施工场界夜间噪声限值是()分贝。",[73,75,77,79],{"key":19,"text":74,"correct":21},"60",{"key":23,"text":76,"correct":28},"55",{"key":26,"text":78,"correct":21},"50",{"key":30,"text":80,"correct":21},"45",{"id":82,"libraryId":5,"type":14,"typeLabel":15,"stem":83,"options":84,"answer":19,"analysis":32},1119538,"在居民密集区使用打桩机进行施工作业时，不宜施工的时间是（）。",[85,87,89,91],{"key":19,"text":86,"correct":28},"晚间22时到早晨6时",{"key":23,"text":88,"correct":21},"晚间21时到早晨7时",{"key":26,"text":90,"correct":21},"晚间21时到早晨6时",{"key":30,"text":92,"correct":21},"晚间22时到早晨7时",{"id":94,"libraryId":5,"type":14,"typeLabel":15,"stem":95,"options":96,"answer":23,"analysis":32},1119539,"根据施工现场环境保护的要求，凡在人口稠密区进行强噪声作业时，须严格控制作业时间。一般情况下，停止强噪声作业的时间是（）。",[97,99,101,103],{"key":19,"text":98,"correct":21},"晚9点到次日早4点之间",{"key":23,"text":100,"correct":28},"晚10点到次日早6点之间",{"key":26,"text":102,"correct":21},"晚11点到次日早4点之间",{"key":30,"text":104,"correct":21},"晚10点到次日早5点之间",{"id":106,"libraryId":5,"type":14,"typeLabel":15,"stem":107,"options":108,"answer":26,"analysis":32},1119540,"施工现场（）人以上的临时食堂，污水排放时可设置简易有效的隔油池，定期掏油、清理杂物，防止污染水体。",[109,110,112,114],{"key":19,"text":78,"correct":21},{"key":23,"text":111,"correct":21},"80",{"key":26,"text":113,"correct":28},"100",{"key":30,"text":115,"correct":21},"150",{"id":117,"libraryId":5,"type":14,"typeLabel":15,"stem":118,"options":119,"answer":19,"analysis":32},1119541,"清理高层建筑施工垃圾的正确做法是()。",[120,122,124,126],{"key":19,"text":121,"correct":28},"将各楼层施工垃圾装入密封容器后吊走",{"key":23,"text":123,"correct":21},"将各楼层施工垃圾焚烧后装入密封容器吊走",{"key":26,"text":125,"correct":21},"将施工垃圾洒水后沿临边窗口倾倒至地面后集中处理",{"key":30,"text":127,"correct":21},"将施工垃圾从电梯井倾倒至地面后集中处理",{"id":129,"libraryId":5,"type":14,"typeLabel":15,"stem":130,"options":131,"answer":19,"analysis":32},1119542,"按照文明管理措施的要求，下列关于现场卫生管理的表述中，正确的是( )。",[132,134,136,138],{"key":19,"text":133,"correct":28},"食堂必须有卫生许可证",{"key":23,"text":135,"correct":21},"卫生间必须有自来水冲洗",{"key":26,"text":137,"correct":21},"建筑垃圾要定期清运",{"key":30,"text":139,"correct":21},"熟食容器要用无毒塑料制品",{"id":141,"libraryId":5,"type":14,"typeLabel":15,"stem":142,"options":143,"answer":30,"analysis":32},1119543,"根据《建设工程施工现场管理规定》，某村庄道路工程现场围挡设置高度不宜低于（）米。",[144,146,148,150],{"key":19,"text":145,"correct":21},"3",{"key":23,"text":147,"correct":21},"2.5",{"key":26,"text":149,"correct":21},"2",{"key":30,"text":151,"correct":28},"1.8",{"id":153,"libraryId":5,"type":14,"typeLabel":15,"stem":154,"options":155,"answer":23,"analysis":32},1119544,"施工现场围挡高度在市区主要路段不宜低于()m，在一般路段不低于()m。",[156,158,160,162],{"key":19,"text":157,"correct":21},"2.0、1.5",{"key":23,"text":159,"correct":28},"2.5、1.8",{"key":26,"text":161,"correct":21},"2.5、1.5",{"key":30,"text":163,"correct":21},"2.0、1.8",{"id":165,"libraryId":5,"type":14,"typeLabel":15,"stem":166,"options":167,"answer":23,"analysis":32},1119545,"在安全文明施工措施中，对于现场大门和围挡设置的叙述错误的是（）。",[168,170,172,174],{"key":19,"text":169,"correct":21},"施工现场设置钢制大门高度不宜低于4m",{"key":23,"text":171,"correct":28},"市区主要路段围挡的高度不宜高于2.5m",{"key":26,"text":173,"correct":21},"施工现场的围挡必须沿工地四周连续设置，不得有缺口",{"key":30,"text":175,"correct":21},"围挡要坚固、平稳、严密、整洁、美观",{"id":177,"libraryId":5,"type":14,"typeLabel":15,"stem":178,"options":179,"answer":19,"analysis":32},1119546,"建立各级文明施工岗位责任制，属于施工现场文明施工的()措施。",[180,182,184,186],{"key":19,"text":181,"correct":28},"组织",{"key":23,"text":183,"correct":21},"管理",{"key":26,"text":185,"correct":21},"经济",{"key":30,"text":187,"correct":21},"技术",{"id":189,"libraryId":5,"type":14,"typeLabel":15,"stem":190,"options":191,"answer":23,"analysis":32},1119547,"施工现场大门内必须设置明显的“五牌一图”，其中“一图”是指（）。",[192,194,196,198],{"key":19,"text":193,"correct":21},"项目部组织机构图",{"key":23,"text":195,"correct":28},"施工现场平面布置图",{"key":26,"text":197,"correct":21},"工程用地规划布置图",{"key":30,"text":199,"correct":21},"建筑总平面布置图",{"id":201,"libraryId":5,"type":14,"typeLabel":15,"stem":202,"options":203,"answer":30,"analysis":32},1119548,"文明施工应当在（）过程实施。",[204,206,208,210],{"key":19,"text":205,"correct":21},"土方开挖至主体封顶施工阶段",{"key":23,"text":207,"correct":21},"项目部进场至主体封顶阶段",{"key":26,"text":209,"correct":21},"主体及装饰装修阶段",{"key":30,"text":211,"correct":28},"项目部进场至施工结束清场阶段",{"id":213,"libraryId":5,"type":14,"typeLabel":15,"stem":214,"options":215,"answer":30,"analysis":32},1119549,"事故发生单位主要负责人有在事故调查中作伪证或者指使他人作伪证违法行为的，对主要负责人、直接负责的主管人员和其他直接责任人员处上一年年收入()的罚款。",[216,218,220,222],{"key":19,"text":217,"correct":21},"30％～60％",{"key":23,"text":219,"correct":21},"40％～70％",{"key":26,"text":221,"correct":21},"50％～80％",{"key":30,"text":223,"correct":28},"60％～100％",{"id":225,"libraryId":5,"type":14,"typeLabel":15,"stem":226,"options":227,"answer":30,"analysis":32},1119550,"在建设工程项目的施工生产活动中，施工环境保护主要是（）。",[228,230,232,234],{"key":19,"text":229,"correct":21},"保护和改善人力资源并避免浪费",{"key":23,"text":231,"correct":21},"保护和改善物质资源并避免浪费",{"key":26,"text":233,"correct":21},"保护和改善施工人员的环境",{"key":30,"text":235,"correct":28},"保护和改善施工现场的环境",{"id":237,"libraryId":5,"type":14,"typeLabel":15,"stem":238,"options":239,"answer":23,"analysis":32},1119551,"施平行承发包模式适用于()的情况。",[240,242,244,246],{"key":19,"text":241,"correct":21},"当项目规模不大，可以选择一个施工单位进行施工总承包或施工总承包管理",{"key":23,"text":243,"correct":28},"由于项目建设的时间要求紧迫，业主急于开工，来不及等所有的施工图全部出齐，只有边设计、边施工",{"key":26,"text":245,"correct":21},"业主缺乏足够的经验和能力应对多家施工单位",{"key":30,"text":247,"correct":21},"将工程分解发包，业主无需过多地照顾各种关系",{"id":249,"libraryId":5,"type":14,"typeLabel":15,"stem":250,"options":251,"answer":26,"analysis":32},1119552,"某建设工程业主将土建、安装、装饰装修等若干单位工程分别发包给甲、乙、丙三家施工单位，则对于甲、乙、丙三家施工单位之间的关系，正确的表述是()。",[252,254,256,258],{"key":19,"text":253,"correct":21},"三家施工单位对工程质量承担连带责任",{"key":23,"text":255,"correct":21},"三家施工单位之间存在直接合同关系",{"key":26,"text":257,"correct":28},"业主负责对三家施工单位的合同管理与组织协调",{"key":30,"text":259,"correct":21},"如甲施工单位阻碍了乙施工单位的施工，乙施工单位应向甲施工单位提出索赔",{"id":261,"libraryId":5,"type":14,"typeLabel":15,"stem":262,"options":263,"answer":23,"analysis":32},1119553,"某建设项目包括多层住宅、高层住宅、小学及幼儿园等若干单位工程，现业主将多层住宅工程发包给甲施工单位，高层住宅工程发包给乙施工单位，小学及幼儿园工程发包给丙施工单位。对业主来说，这样的发包方式在费用控制与进度控制方面的特点是()。",[264,266,268,270],{"key":19,"text":265,"correct":21},"对投资的早期控制不利，且不利于缩短建设周期",{"key":23,"text":267,"correct":28},"对投资的早期控制不利，但有利于缩短建设周期",{"key":26,"text":269,"correct":21},"对投资的早期控制较为有利，且不利于缩短建设周期",{"key":30,"text":271,"correct":21},"对投资的早期控制较为有利，但有利于缩短建设周期",{"id":273,"libraryId":5,"type":14,"typeLabel":15,"stem":274,"options":275,"answer":23,"analysis":32},1119554,"某建设工程包括土建、安装、装饰装修等若干单位工程，现业主将土建工程发包给甲施工单位，安装工程发包给乙施工单位，装饰装修工程发包给丙施工单位。对业主来说，这样的发包方式在费用控制与进度控制方面的特点是（）。",[276,277,278,279],{"key":19,"text":265,"correct":21},{"key":23,"text":267,"correct":28},{"key":26,"text":269,"correct":21},{"key":30,"text":280,"correct":21},"对投资的早期控制较为有利，也有利于缩短建设周期",{"id":282,"libraryId":5,"type":14,"typeLabel":15,"stem":283,"options":284,"answer":26,"analysis":32},1119555,"实行施工平行承发包对建设工程项目进度控制的影响表现为（）。",[285,287,289,291],{"key":19,"text":286,"correct":21},"业主要负责所有施工承包合同的招标、合同谈判、签约，招标及合同管理工作量大，对业主不利",{"key":23,"text":288,"correct":21},"每一部分工程的施工，发包人都可以通过招标选择最好的施工单位承包，对降低工程造价有利",{"key":26,"text":290,"correct":28},"由于要进行多次招标，业主用于招标的时间较多",{"key":30,"text":292,"correct":21},"业主直接控制所有工程的发包，确定所有工程的承包商",{"id":294,"libraryId":5,"type":14,"typeLabel":15,"stem":295,"options":296,"answer":30,"analysis":32},1119556,"业主直接控制所有工程的发包，可决定所有工程的承包商的选择，属于施工平行承发包模式中的()的内容。",[297,299,301,303],{"key":19,"text":298,"correct":21},"费用控制",{"key":23,"text":300,"correct":21},"进度控制",{"key":26,"text":302,"correct":21},"合同管理",{"key":30,"text":304,"correct":28},"组织与协调",{"id":306,"libraryId":5,"type":14,"typeLabel":15,"stem":307,"options":308,"answer":30,"analysis":32},1119557,"一般情况下，发包人在选择施工承包单位时，通常根据（）进行施工招标。",[309,311,313,315],{"key":19,"text":310,"correct":21},"工程项目特点",{"key":23,"text":312,"correct":21},"施工进度计划",{"key":26,"text":314,"correct":21},"控制目标的要求",{"key":30,"text":316,"correct":28},"施工图设计",{"id":318,"libraryId":5,"type":14,"typeLabel":15,"stem":319,"options":320,"answer":23,"analysis":32},1119558,"某地铁工程施工中，业主将14座车站的土建工程分别发包给14个土建施工单位，14座车站的机电安装工程分别发包给14个机电安装单位，就是典型的()模式。",[321,323,325,327],{"key":19,"text":322,"correct":21},"BOT",{"key":23,"text":324,"correct":28},"施工平行承发包",{"key":26,"text":326,"correct":21},"施工总承包管理",{"key":30,"text":328,"correct":21},"施工总承包",{"id":330,"libraryId":5,"type":14,"typeLabel":15,"stem":331,"options":332,"answer":19,"analysis":32},1119559,"业主把某建设项目土建工程发包给A施工单位，安装工程发包给B施工单位，装饰装修工程发包给C施工单位。该业主采用的施工任务委托模式是()。",[333,335,337,339],{"key":19,"text":334,"correct":28},"施工平行承发包模式",{"key":23,"text":336,"correct":21},"施工总承包模式",{"key":26,"text":338,"correct":21},"施工总承包管理模式",{"key":30,"text":340,"correct":21},"工程总承包模式",{"id":342,"libraryId":5,"type":14,"typeLabel":15,"stem":343,"options":344,"answer":23,"analysis":32},1119560,"某办公楼建设项目中，业主将打桩工程发包给甲施工单位，将主体土建工程发包给乙施工单位，将机电安装工程发包给丙施工单位，将精装修工程发包给丁施工单位。该业主采用的承包模式是（）。",[345,347,348,349],{"key":19,"text":346,"correct":21},"施工总承包模式承",{"key":23,"text":334,"correct":28},{"key":26,"text":338,"correct":21},{"key":30,"text":350,"correct":21},"EPC承包模式",{"id":352,"libraryId":5,"type":14,"typeLabel":15,"stem":353,"options":354,"answer":23,"analysis":32},1119561,"某地铁工程，业主将10座车站的土建工程分别发包给10个土建施工单位，机电安装工程分别发包给10个机电安装单位，则业主采用的承发包模式是()。",[355,356,357,358],{"key":19,"text":336,"correct":21},{"key":23,"text":334,"correct":28},{"key":26,"text":338,"correct":21},{"key":30,"text":350,"correct":21},{"id":360,"libraryId":5,"type":14,"typeLabel":15,"stem":361,"options":362,"answer":30,"analysis":32},1119562,"关于施工平行承发包特点的说法，正确的是()。",[363,365,367,369],{"key":19,"text":364,"correct":21},"业主在施工图完成后即可知道整个工程的总造价",{"key":23,"text":366,"correct":21},"业主可以分次招标，每次招标工作量较小，业主用于招标的时间较少",{"key":26,"text":368,"correct":21},"业主直接管理所有的施工合同，管理风险小",{"key":30,"text":370,"correct":28},"业主直接控制所有工程的发包，可决定所有工程的承包商的选择",{"id":372,"libraryId":5,"type":14,"typeLabel":15,"stem":373,"options":374,"answer":30,"analysis":32},1119563,"施工平行承发包模式适用于()的情况。",[375,376,378,379],{"key":19,"text":247,"correct":21},{"key":23,"text":377,"correct":21},"项目规模不大",{"key":26,"text":245,"correct":21},{"key":30,"text":243,"correct":28},{"id":381,"libraryId":5,"type":14,"typeLabel":15,"stem":382,"options":383,"answer":23,"analysis":32},1119564,"通常施工总承包合同在开工前就有较明确的（）。",[384,386,388,390],{"key":19,"text":385,"correct":21},"单价",{"key":23,"text":387,"correct":28},"合同价",{"key":26,"text":389,"correct":21},"决算价",{"key":30,"text":391,"correct":21},"总造价",{"id":393,"libraryId":5,"type":14,"typeLabel":15,"stem":394,"options":395,"answer":26,"analysis":32},1119565,"不属于施工总承包的特点的是( )。",[396,398,400,401],{"key":19,"text":397,"correct":21},"在通过招标选择施工总承包单位时，一般都以施工图设计为投标报价的基础，投标人的投标报价较有依据",{"key":23,"text":399,"correct":21},"在开工前就有较明确的合同价，有利于业主对总造价的早期控制",{"key":26,"text":370,"correct":28},{"key":30,"text":402,"correct":21},"若在施工过程中发生设计变更，则可能发生索赔",{"id":404,"libraryId":5,"type":14,"typeLabel":15,"stem":405,"options":406,"answer":23,"analysis":32},1119566,"某开发公司计划建设一幢高档写字楼项目，采用施工总承包管理模式，并在未完成施工图设计的情况下采用“费率招标”方式进行招标。这种方式对业主在费用控制方面的影响是（）。",[407,408,410,412],{"key":19,"text":399,"correct":21},{"key":23,"text":409,"correct":28},"在开工前合同价格不明确，不利于业主对总造价的早期控制",{"key":26,"text":411,"correct":21},"费用控制的好坏在很大程度上取决于施工总承包单位的选择",{"key":30,"text":413,"correct":21},"在施工过程中发生设计变更，产生索赔的可能性小",{"id":415,"libraryId":5,"type":14,"typeLabel":15,"stem":416,"options":417,"answer":19,"analysis":32},1119567,"对业主来说，要等最后一份合同签订后才知道整个工程的总造价，对投资的早期控制不利，属于施工平行承发包模式中的()的特点。",[418,419,420,422],{"key":19,"text":298,"correct":28},{"key":23,"text":300,"correct":21},{"key":26,"text":421,"correct":21},"质量控制",{"key":30,"text":302,"correct":21},{"id":424,"libraryId":5,"type":14,"typeLabel":15,"stem":425,"options":426,"answer":30,"analysis":32},1119568,"下列关于总承包模式施工承发包的表述正确的是（）。",[427,429,431,433],{"key":19,"text":428,"correct":21},"项目质量的好坏很大程度上取决于业主的管理水平",{"key":23,"text":430,"correct":21},"施工总承包合同一般实行单价合同",{"key":26,"text":432,"correct":21},"业主需进行多次招标，合同管理量较大",{"key":30,"text":434,"correct":28},"业主只负责对施工总承包单位的管理及组织协调，对业主比较有利",{"id":436,"libraryId":5,"type":14,"typeLabel":15,"stem":437,"options":438,"answer":19,"analysis":32},1119569,"某房地产开发商计划建设一幢高档写字楼项目，拟采用施工总承包模式，则这种方式对开发商在费用控制方面的影响是()。",[439,440,441,443],{"key":19,"text":399,"correct":28},{"key":23,"text":409,"correct":21},{"key":26,"text":442,"correct":21},"费用控制的好坏在很大程度上取决于对施工分包单位的选择",{"key":30,"text":413,"correct":21},{"id":445,"libraryId":5,"type":14,"typeLabel":15,"stem":446,"options":447,"answer":26,"analysis":32},1119570,"对施工任务的平行发包，发包人可以根据建设项目的结构进行分解分包，也可以根据建设项目施工的（）进行分解发包",[448,450,452,454],{"key":19,"text":449,"correct":21},"不同部位",{"key":23,"text":451,"correct":21},"不同投资额",{"key":26,"text":453,"correct":28},"不同专业系统",{"key":30,"text":455,"correct":21},"不同特点",{"id":457,"libraryId":5,"type":14,"typeLabel":15,"stem":458,"options":459,"answer":19,"analysis":32},1119571,"施工总承包模式在费用控制方面的主要特点是()。",[460,461,462,464],{"key":19,"text":399,"correct":28},{"key":23,"text":409,"correct":21},{"key":26,"text":463,"correct":21},"投标人投标时，投标报价缺乏依据",{"key":30,"text":413,"correct":21},{"id":466,"libraryId":5,"type":14,"typeLabel":15,"stem":467,"options":468,"answer":26,"analysis":32},1119572,"关于施工总承包模式特点的说法，正确的是（）",[469,471,473,475],{"key":19,"text":470,"correct":21},"施工总承包单位负责项目总进度计划的编制、控制、协调",{"key":23,"text":472,"correct":21},"项目质量取决于业主的管理水平和施工总承包单位的技术水平",{"key":26,"text":474,"correct":28},"在开工前就有明确的合同价，有利于业主对总造价的早期控制",{"key":30,"text":476,"correct":21},"业主需负责施工总承包单位和分包单位的管理和组织协调",{"id":478,"libraryId":5,"type":14,"typeLabel":15,"stem":479,"options":480,"answer":19,"analysis":32},1119573,"关于施工平行承发包的应用，下列说法错误的是（）。",[481,483,485,487],{"key":19,"text":482,"correct":28},"对施工任务的平行发包，发包方不能根据建设项目的结构进行分解发包",{"key":23,"text":484,"correct":21},"对施工任务的平行发包，发包方可以根据建设项目的结构进行分解发包",{"key":26,"text":486,"correct":21},"对施工任务的平行发包，发包方可以根据建设项目施工的不同专业系统进行分解发包",{"key":30,"text":488,"correct":21},"最后一份合同签订后，业主才知道整个工程的总造价",{"id":490,"libraryId":5,"type":14,"typeLabel":15,"stem":491,"options":492,"answer":26,"analysis":32},1119574,"关于施工总承包模式的说法，下列选项正确的是()。",[493,495,497,499],{"key":19,"text":494,"correct":21},"工程质量的好坏取决于业主的管理水平",{"key":23,"text":496,"correct":21},"施工总承包模式适用于建设周期紧迫的项目",{"key":26,"text":498,"correct":28},"施工总承包模式下业主对施工总承包单位的依赖较大",{"key":30,"text":500,"correct":21},"施工总承包合同一般采用单价合同",{"id":502,"libraryId":5,"type":14,"typeLabel":15,"stem":503,"options":504,"answer":23,"analysis":32},1119575,"施工总承包，是指发包人将全部施工任务发包给一个施工单位或由多个施工单位组成的施工联合体或施工合作体，施工总承包单位主要依靠自己的力量完成施工任务。当然，经发包人同意，施工总承包单位可以根据需要将施工任务的一部分分包给其他符合资质的()。",[505,507,509,511],{"key":19,"text":506,"correct":21},"设计单位",{"key":23,"text":508,"correct":28},"分包人",{"key":26,"text":510,"correct":21},"供货商",{"key":30,"text":512,"correct":21},"建设单位",{"id":514,"libraryId":5,"type":14,"typeLabel":15,"stem":515,"options":516,"answer":26,"analysis":32},1119576,"关于施工总承包特点的说法，正确的是（）。",[517,519,521,523],{"key":19,"text":518,"correct":21},"施工可以在项目设计阶段未结束前进行，缩短建设周期",{"key":23,"text":520,"correct":21},"施工总承包合同一般只实行单价合同",{"key":26,"text":522,"correct":28},"业主只负责对施工总承包单位的管理及组织协调",{"key":30,"text":428,"correct":21},{"id":525,"libraryId":5,"type":14,"typeLabel":15,"stem":526,"options":527,"answer":23,"analysis":32},1119577,"关于施工总承包管理模式下合同管理的说法，错误的是()。",[528,530,532,534],{"key":19,"text":529,"correct":21},"所有分包合同的招标投标、合同谈判以及签约工作均由业主负责",{"key":23,"text":531,"correct":28},"业主方的招标及合同管理工作量较大",{"key":26,"text":533,"correct":21},"对分包人的工程款支付可由施工总包管理单位支付或由业主直接支付，前者有利于施工总包管理单位对分包人的管理",{"key":30,"text":535,"correct":21},"业主只需要进行一次招标，与施工总承包商签约，因此招标及合同管理工作量将会减小",{"id":537,"libraryId":5,"type":14,"typeLabel":15,"stem":538,"options":539,"answer":19,"analysis":32},1119578,"施工总承包模式的一般工作程序为()。",[540,542,544,546],{"key":19,"text":541,"correct":28},"施工图设计完成→施工总承包的招投标→施工→竣工验收",{"key":23,"text":543,"correct":21},"施工图设计完成→施工→施工总承包的招投标→竣工验收",{"key":26,"text":545,"correct":21},"施工总承包的招投标→施工图设计完成→施工→竣工验收",{"key":30,"text":547,"correct":21},"施工总承包的招投标→施工→施工图设计完成→竣工验收",{"id":549,"libraryId":5,"type":14,"typeLabel":15,"stem":550,"options":551,"answer":30,"analysis":32},1119579,"在很多的工程实践中采用()对业主方的合同管理和投资控制十分不利。",[552,553,555,557],{"key":19,"text":328,"correct":21},{"key":23,"text":554,"correct":21},"分体承包",{"key":26,"text":556,"correct":21},"开口招标",{"key":30,"text":558,"correct":28},"费率招标",{"id":560,"libraryId":5,"type":14,"typeLabel":15,"stem":561,"options":562,"answer":19,"analysis":32},1119580,"施工总承包的一般工作程序为（）。",[563,565,567,569],{"key":19,"text":564,"correct":28},"施工图设计完成→施工总承包的招标投标→施工→竣工验收",{"key":23,"text":566,"correct":21},"施工图设计完成→施工→施工总承包的招标投标→竣工验收",{"key":26,"text":568,"correct":21},"施工总承包的招标投标→施工图设计完成→施工→竣工验收",{"key":30,"text":570,"correct":21},"施工总承包的招标投标→施工→施工图设计完成→竣工验收",{"id":572,"libraryId":5,"type":14,"typeLabel":15,"stem":573,"options":574,"answer":26,"analysis":32},1119581,"在施工总承包管理模式中，对于分包单位的选择，决策者应该是()",[575,577,579,581],{"key":19,"text":576,"correct":21},"工程师",{"key":23,"text":578,"correct":21},"施工总承包管理单位",{"key":26,"text":580,"correct":28},"业主",{"key":30,"text":582,"correct":21},"施工总承包单位",{"id":584,"libraryId":5,"type":14,"typeLabel":15,"stem":585,"options":586,"answer":26,"analysis":32},1119582,"施工总承包管理模式下，施工总承包管理单位()。",[587,589,591,593],{"key":19,"text":588,"correct":21},"承担主体工程施工",{"key":23,"text":590,"correct":21},"承担所有工程施工",{"key":26,"text":592,"correct":28},"一般不参与具体工程的施工",{"key":30,"text":594,"correct":21},"承担半数以上单位工程的施工",[596,599,602,605,608,611],{"id":14,"name":597,"category":7,"favorite":598},"领导干部任职前廉政法规知识测试题",92,{"id":600,"name":601,"category":7,"favorite":14},595,"建筑结构与设备",{"id":603,"name":604,"category":7,"favorite":14},715,"招标采购专业知识与法律法规",{"id":606,"name":607,"category":7,"favorite":14},848,"市政方向-通用基础",{"id":609,"name":610,"category":7,"favorite":8},534,"BIM工程师",{"id":612,"name":610,"category":7,"favorite":8},535]