[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-789-32":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":563},{"id":5,"name":6,"category":7,"favorite":8},789,"二建建设工程施工管理","建筑工程",0,32,50,2973,[13,34,46,58,70,82,94,106,114,124,136,148,158,170,182,194,205,217,228,240,248,260,270,280,292,304,316,328,340,352,360,372,381,389,397,409,417,429,438,450,458,468,480,488,499,507,515,527,539,551],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":20,"analysis":33},1118630,1,"单选题","下列属于双代号网络计划中工作之间的逻辑关系的是()。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","工艺关系",true,{"key":24,"text":25,"correct":26},"B","流程关系",false,{"key":28,"text":29,"correct":26},"C","紧前紧后关系",{"key":31,"text":32,"correct":26},"D","并列关系","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},1118631,"在某工程单代号网络计划中，说法错误的是()。",[38,40,42,44],{"key":20,"text":39,"correct":22},"关键线路只有一条",{"key":24,"text":41,"correct":26},"在计划实施过程中，关键线路可以改变",{"key":28,"text":43,"correct":26},"关键工作的机动时间最少",{"key":31,"text":45,"correct":26},"相邻关键工作之问的时间间隔为零",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":20,"analysis":33},1118632,"下列关于双代号网络计划绘图规则的说法，正确的有（）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"网络图必须正确表达各工作间的逻辑关系",{"key":24,"text":53,"correct":26},"网络图中可以出现循环回路",{"key":28,"text":55,"correct":26},"网络图中一个节点只有一条箭线引入和一条箭线引出",{"key":31,"text":57,"correct":26},"网络图中可以出现没有箭头节点或没有箭尾节点的箭线",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":31,"analysis":33},1118633,"在不影响其紧后工作最早开始的前提下，工作可以利用的机动时间是（）。",[62,64,66,68],{"key":20,"text":63,"correct":26},"最早开始时间",{"key":24,"text":65,"correct":26},"最早完成时间",{"key":28,"text":67,"correct":26},"总时差",{"key":31,"text":69,"correct":22},"自由时差",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":31,"analysis":33},1118634,"单代号网络计划中，工作的自由时差和该工作与其紧后工作之间的时间间隔的关系是( )。",[74,76,78,80],{"key":20,"text":75,"correct":26},"自由时差就等于时间间隔",{"key":24,"text":77,"correct":26},"自由时差与时间间隔无直接关系",{"key":28,"text":79,"correct":26},"自由时差等于该工作与其紧后工作之间的时间间隔的最大值",{"key":31,"text":81,"correct":22},"自由时差等于该工作与其紧后工作之间的时间间隔的最小值",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":20,"analysis":33},1118635,"在工程网络计划执行过程中，如果某项工作实际进度拖延的时间没有超过其自由时差，则()。",[86,88,90,92],{"key":20,"text":87,"correct":22},"不影响其紧后工作的最早开始",{"key":24,"text":89,"correct":26},"影响其紧后工作的最早开始时间",{"key":28,"text":91,"correct":26},"该工作的总时差不会变",{"key":31,"text":93,"correct":26},"可能会影响工程总工期",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":20,"analysis":33},1118636,"某网络计划中，工作M的最早完成时间是第8天，最迟完成是第13天，工作的持续时间为4天，与所有的紧后工作的间隔时间最小值为2天，则该工作的自由时差为()天。",[98,100,102,104],{"key":20,"text":99,"correct":22},"2",{"key":24,"text":101,"correct":26},"3",{"key":28,"text":103,"correct":26},"4",{"key":31,"text":105,"correct":26},"5",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":20,"analysis":33},1118637,"某网络计划中，工作M的最早完成时间是第9天，最迟完成时间是第15天，工作的持续时间为4d，其所有紧后工作时间间隔最小值为2d。则该工作的自由时差为（）天。",[110,111,112,113],{"key":20,"text":99,"correct":22},{"key":24,"text":101,"correct":26},{"key":28,"text":103,"correct":26},{"key":31,"text":105,"correct":26},{"id":115,"libraryId":5,"type":15,"typeLabel":16,"stem":116,"options":117,"answer":28,"analysis":33},1118638,"某工程施工网络计划经监理工程师批准后实施。已知工作A有5天的自由时差和8天的总时差，由于第三方原因，使工作A的实际完成时间比原计划延长了12天。在无其它干扰的情况下，其紧后工作的最早开始时间将推迟()天。",[118,119,120,122],{"key":20,"text":101,"correct":26},{"key":24,"text":103,"correct":26},{"key":28,"text":121,"correct":22},"7",{"key":31,"text":123,"correct":26},"12",{"id":125,"libraryId":5,"type":15,"typeLabel":16,"stem":126,"options":127,"answer":31,"analysis":33},1118639,"某工程网络计划中工作M的总时差为3d，自由时差为0。该计划执行过程中，只有工作M的实际进度拖后4d，则工作M的实际进度将其紧后工作的最早开始时间推迟和使总工期延长的时间分别为()。",[128,130,132,134],{"key":20,"text":129,"correct":26},"3d和0d",{"key":24,"text":131,"correct":26},"3d和1d",{"key":28,"text":133,"correct":26},"4d和0d",{"key":31,"text":135,"correct":22},"4d和1d",{"id":137,"libraryId":5,"type":15,"typeLabel":16,"stem":138,"options":139,"answer":24,"analysis":33},1118640,"某工程网络计划中，工作M的总时差为6天，自由时差为4天，在计划执行的检查中发现，只有工作M的实际进度拖后了5天，则下面说法正确的是()",[140,142,144,146],{"key":20,"text":141,"correct":26},"会使总工期拖后1天，使后续工作最早开工时间拖后1天",{"key":24,"text":143,"correct":22},"不影响总工期，但会使后续工作的最早开工时间拖后1天",{"key":28,"text":145,"correct":26},"使总工期拖后1天，但不影响后续工作的正常进行",{"key":31,"text":147,"correct":26},"不影响总工期，也不影响后续工作的正常进行",{"id":149,"libraryId":5,"type":15,"typeLabel":16,"stem":150,"options":151,"answer":28,"analysis":33},1118641,"某工程网络计划中，工作F的最早开始时间为第10天，持续时间为5天；工作F有二项紧后工作，它们的最早开始时间分别为第22天、第24天，最迟开始时间分别为第23天、25天。则工作F的总时差为()天。",[152,153,155,157],{"key":20,"text":105,"correct":26},{"key":24,"text":154,"correct":26},"6",{"key":28,"text":156,"correct":22},"8",{"key":31,"text":103,"correct":26},{"id":159,"libraryId":5,"type":15,"typeLabel":16,"stem":160,"options":161,"answer":20,"analysis":33},1118642,"某工程网络计划中，工作P的最迟完成时间为第25天，其持续时间为6天。该工作有三项紧前工作，它们的最早完成时间分别为第10天、第12天和第13天，则该工作P的总时差为()。",[162,164,166,168],{"key":20,"text":163,"correct":22},"6天",{"key":24,"text":165,"correct":26},"10天",{"key":28,"text":167,"correct":26},"12天",{"key":31,"text":169,"correct":26},"14天",{"id":171,"libraryId":5,"type":15,"typeLabel":16,"stem":172,"options":173,"answer":20,"analysis":33},1118643,"在工程网络计划的执行过程中，监理工程师检查实际进度时，只发现工作M的总时差由原计划的3天变为-2天，说明工作M的实际进度()。",[174,176,178,180],{"key":20,"text":175,"correct":22},"拖后5天，影响工期2天",{"key":24,"text":177,"correct":26},"拖后2天，影响工期2天",{"key":28,"text":179,"correct":26},"拖后3天，影响工期2天",{"key":31,"text":181,"correct":26},"拖后2天，影响工期1天",{"id":183,"libraryId":5,"type":15,"typeLabel":16,"stem":184,"options":185,"answer":24,"analysis":33},1118644,"某工程双代号时标网络计划如下图所示，其中工作B的总时差和自由时差()周。",[186,188,190,192],{"key":20,"text":187,"correct":26},"均为1",{"key":24,"text":189,"correct":22},"分别为2和1",{"key":28,"text":191,"correct":26},"分别为4和1",{"key":31,"text":193,"correct":26},"均为4",{"id":195,"libraryId":5,"type":15,"typeLabel":16,"stem":196,"options":197,"answer":20,"analysis":33},1118645,"已知在双代号网络计划中，某工作有2项紧后工作，它们的最迟开始时间分别为11天和13天。如果该工作的持续时间为3天，则该工作最迟开始时间为()。",[198,200,201,203],{"key":20,"text":199,"correct":22},"8天",{"key":24,"text":165,"correct":26},{"key":28,"text":202,"correct":26},"11天",{"key":31,"text":204,"correct":26},"13天",{"id":206,"libraryId":5,"type":15,"typeLabel":16,"stem":207,"options":208,"answer":31,"analysis":33},1118646,"最迟完成时间是指（）。",[209,211,213,215],{"key":20,"text":210,"correct":26},"在各项紧前的工作全部完成后，工作有可能开始的最早时刻",{"key":24,"text":212,"correct":26},"在各项紧前的工作全部完成后，工作有可能完成的最早时刻",{"key":28,"text":214,"correct":26},"在不影响整个任务按期完成的前提下，工作必须开始的最迟时刻",{"key":31,"text":216,"correct":22},"在不影响整个任务按期完成的前提下，工作必须完成的最迟时刻",{"id":218,"libraryId":5,"type":15,"typeLabel":16,"stem":219,"options":220,"answer":24,"analysis":33},1118647,"工作()等于该工作最早开始时间加上其持续时间。",[221,223,224,226],{"key":20,"text":222,"correct":26},"最迟开始时间",{"key":24,"text":65,"correct":22},{"key":28,"text":225,"correct":26},"最早结束时间",{"key":31,"text":227,"correct":26},"最迟结束时间",{"id":229,"libraryId":5,"type":15,"typeLabel":16,"stem":230,"options":231,"answer":24,"analysis":33},1118648,"已知某工程双代号网络图如下，按照计划安排F工作的最早开始时间为（）。",[232,234,236,238],{"key":20,"text":233,"correct":26},"第10天",{"key":24,"text":235,"correct":22},"第12天",{"key":28,"text":237,"correct":26},"第14天",{"key":31,"text":239,"correct":26},"第17天",{"id":241,"libraryId":5,"type":15,"typeLabel":16,"stem":242,"options":243,"answer":28,"analysis":33},1118649,"已知下列双代号网络图，由于设计图纸的变更，造成D工作延误6天，则总工期将延长（）天。",[244,245,246,247],{"key":20,"text":99,"correct":26},{"key":24,"text":101,"correct":26},{"key":28,"text":103,"correct":22},{"key":31,"text":105,"correct":26},{"id":249,"libraryId":5,"type":15,"typeLabel":16,"stem":250,"options":251,"answer":31,"analysis":33},1118650,"在某双代号网络计划中，工作A的最早开始时间为第10天，其持续时间为6天，该工作有两项紧后工作，它们的最早开始时间分别为第26天和第31天，最迟开始时间分别为第27天和第34天，则工作A的总时差和自由时差（）天。",[252,254,256,258],{"key":20,"text":253,"correct":26},"均为11",{"key":24,"text":255,"correct":26},"分别为10和9",{"key":28,"text":257,"correct":26},"均为10",{"key":31,"text":259,"correct":22},"分别为11和10",{"id":261,"libraryId":5,"type":15,"typeLabel":16,"stem":262,"options":263,"answer":28,"analysis":33},1118651,"已知工作A的紧后工作是B和 C，工作B的最迟开始时间为14天，最早开始时间为10天，工作C的最迟完成时间为16天，最早完成时间为14天，工作A的自由时差为5天，则工作A的总时差为（）天。",[264,265,267,268],{"key":20,"text":105,"correct":26},{"key":24,"text":266,"correct":26},"9",{"key":28,"text":121,"correct":22},{"key":31,"text":269,"correct":26},"11",{"id":271,"libraryId":5,"type":15,"typeLabel":16,"stem":272,"options":273,"answer":28,"analysis":33},1118652,"假设工作C的紧前工作仅有A和 B，它们的最早开始时间分别为6天和7天，持续时间分别为4天和5天，则工作C的最早开始时间为（）天。",[274,276,277,278],{"key":20,"text":275,"correct":26},"10",{"key":24,"text":269,"correct":26},{"key":28,"text":123,"correct":22},{"key":31,"text":279,"correct":26},"13",{"id":281,"libraryId":5,"type":15,"typeLabel":16,"stem":282,"options":283,"answer":31,"analysis":33},1118653,"在双代号网络计划中，如果其计划工期与计算工期相等，且工作i-j的完成节点在关键线路上，则工作i-j的自由时差（）。",[284,286,288,290],{"key":20,"text":285,"correct":26},"等于零",{"key":24,"text":287,"correct":26},"小于零",{"key":28,"text":289,"correct":26},"小于其相应的总时差",{"key":31,"text":291,"correct":22},"等于其相应的总时差",{"id":293,"libraryId":5,"type":15,"typeLabel":16,"stem":294,"options":295,"answer":20,"analysis":33},1118654,"双代号网络图中，某非关键工作的拖延时间不超过自由时差，则（）。",[296,298,300,302],{"key":20,"text":297,"correct":22},"后续工作最早可能开始时间不变",{"key":24,"text":299,"correct":26},"仅改变后续工作最早可能开始时间",{"key":28,"text":301,"correct":26},"后续工作最迟必须开始时间改变",{"key":31,"text":303,"correct":26},"紧后工作最早可能开始时间改变",{"id":305,"libraryId":5,"type":15,"typeLabel":16,"stem":306,"options":307,"answer":24,"analysis":33},1118655,"双代号网络计划如下图所示(时间单位:天),其计算工期是()天。",[308,310,312,314],{"key":20,"text":309,"correct":26},"16",{"key":24,"text":311,"correct":22},"17",{"key":28,"text":313,"correct":26},"18",{"key":31,"text":315,"correct":26},"20",{"id":317,"libraryId":5,"type":15,"typeLabel":16,"stem":318,"options":319,"answer":28,"analysis":33},1118656,"在双代号网络计划中，某工作A最早完成时间为15，其有三项紧后工作，它们的最迟开始时间分别为17、20、21，总时差分别为1、2、4，那么工作A的自由时差和总时差为()",[320,322,324,326],{"key":20,"text":321,"correct":26},"2、2",{"key":24,"text":323,"correct":26},"0、2",{"key":28,"text":325,"correct":22},"1、2",{"key":31,"text":327,"correct":26},"1、4",{"id":329,"libraryId":5,"type":15,"typeLabel":16,"stem":330,"options":331,"answer":28,"analysis":33},1118657,"在计算双代号网络计划的时间参数时，工作的最迟完成时间等于其所有紧后工作的（）",[332,334,336,338],{"key":20,"text":333,"correct":26},"最早开始时间的最小值",{"key":24,"text":335,"correct":26},"最早开始时间的最大值",{"key":28,"text":337,"correct":22},"最迟开始时间的最小值",{"key":31,"text":339,"correct":26},"最迟开始时间的最大值",{"id":341,"libraryId":5,"type":15,"typeLabel":16,"stem":342,"options":343,"answer":20,"analysis":33},1118658,"已知工程网络计划中，工作M、N、P无紧后工作，则该网络计划的计算工期应等于这三项工作的()。",[344,346,348,350],{"key":20,"text":345,"correct":22},"最早完成时间的最大值",{"key":24,"text":347,"correct":26},"最迟完成时间的最大值",{"key":28,"text":349,"correct":26},"最早完成时间的最小值",{"key":31,"text":351,"correct":26},"最迟完成时间的最小值",{"id":353,"libraryId":5,"type":15,"typeLabel":16,"stem":354,"options":355,"answer":28,"analysis":33},1118659,"某工程网络计划共有十项工作，其中A工作为起始工作，其紧后工作为 B，B工作的紧后工作为 C，持续时间分别为3d、4d、4d，B工作的总时差为2d，则B工作的最迟开始时间为()d。",[356,357,358,359],{"key":20,"text":101,"correct":26},{"key":24,"text":103,"correct":26},{"key":28,"text":105,"correct":22},{"key":31,"text":121,"correct":26},{"id":361,"libraryId":5,"type":15,"typeLabel":16,"stem":362,"options":363,"answer":24,"analysis":33},1118660,"在工程网络计划中，工作的最迟开始时间等于本工作的()。",[364,366,368,370],{"key":20,"text":365,"correct":26},"最迟完成时间与其时间间隔之差",{"key":24,"text":367,"correct":22},"最迟完成时间与其持续时间之差",{"key":28,"text":369,"correct":26},"最早开始时间与其持续时间之和",{"key":31,"text":371,"correct":26},"最早开始时间与其时间间隔之和",{"id":373,"libraryId":5,"type":15,"typeLabel":16,"stem":374,"options":375,"answer":28,"analysis":33},1118661,"已知某网络计划中工作M的自由时差为3天，总时差为5天。通过检查分析，发现该工作的实际进度拖后，且影响总工期1天。在其他工作均正常的前提下，工作M的实际进度拖后()天。",[376,378,379,380],{"key":20,"text":377,"correct":26},"1",{"key":24,"text":103,"correct":26},{"key":28,"text":154,"correct":22},{"key":31,"text":266,"correct":26},{"id":382,"libraryId":5,"type":15,"typeLabel":16,"stem":383,"options":384,"answer":28,"analysis":33},1118662,"下列网络计划中，工作E的最迟开始时间是第()天。",[385,386,387,388],{"key":20,"text":103,"correct":26},{"key":24,"text":105,"correct":26},{"key":28,"text":154,"correct":22},{"key":31,"text":121,"correct":26},{"id":390,"libraryId":5,"type":15,"typeLabel":16,"stem":391,"options":392,"answer":24,"analysis":33},1118663,"某工程网络计划中，N工作的最早开始时间和最迟开始时间分别为第12天和第15天，其持续时间为6天。N工作有3项紧后工作，它们的最早开始时间分别为第21天、第24天、第28天，则N工作的自由时差是()天。",[393,394,395,396],{"key":20,"text":377,"correct":26},{"key":24,"text":101,"correct":22},{"key":28,"text":103,"correct":26},{"key":31,"text":156,"correct":26},{"id":398,"libraryId":5,"type":15,"typeLabel":16,"stem":399,"options":400,"answer":31,"analysis":33},1118664,"在双代号或单代号网络计划中，判别关键工作的条件是该工作（）。",[401,403,405,407],{"key":20,"text":402,"correct":26},"自由时差最小",{"key":24,"text":404,"correct":26},"与其紧后工作之间的时间间隔为零",{"key":28,"text":406,"correct":26},"持续时间最长",{"key":31,"text":408,"correct":22},"最迟开始时间与最早开始时间的差值最小",{"id":410,"libraryId":5,"type":15,"typeLabel":16,"stem":411,"options":412,"answer":20,"analysis":33},1118665,"某工程网络计划中，工作W的最早开始时间和最迟开始时间分别为第12天和第15天，其持续时间为5天，工作W有3个紧后工作，它们的最早开始时间分别为第21天，24天和第28天，W的自由时差为（）天。",[413,414,415,416],{"key":20,"text":103,"correct":22},{"key":24,"text":154,"correct":26},{"key":28,"text":121,"correct":26},{"key":31,"text":269,"correct":26},{"id":418,"libraryId":5,"type":15,"typeLabel":16,"stem":419,"options":420,"answer":20,"analysis":33},1118666,"某双代号网络计划如图所示（时间单位：d），则该计划的关键线路是()。",[421,423,425,427],{"key":20,"text":422,"correct":22},"①→②→④→⑤→⑥→⑦",{"key":24,"text":424,"correct":26},"①→②→④→⑤→⑦",{"key":28,"text":426,"correct":26},"①→③→④→⑤→⑥→⑦",{"key":31,"text":428,"correct":26},"①→③→④→⑤→⑦",{"id":430,"libraryId":5,"type":15,"typeLabel":16,"stem":431,"options":432,"answer":31,"analysis":33},1118667,"下列网络计划的计算工期是（）天。",[433,434,435,436],{"key":20,"text":156,"correct":26},{"key":24,"text":269,"correct":26},{"key":28,"text":123,"correct":26},{"key":31,"text":437,"correct":22},"14",{"id":439,"libraryId":5,"type":15,"typeLabel":16,"stem":440,"options":441,"answer":20,"analysis":33},1118668,"关于关键工作和关键线路，下列说法正确的是（）。",[442,444,446,448],{"key":20,"text":443,"correct":22},"关键线路上的工作全部是关键工作",{"key":24,"text":445,"correct":26},"关键工作不能在非关键线路上",{"key":28,"text":447,"correct":26},"关键线路上不允许出现虚工作",{"key":31,"text":449,"correct":26},"关键线路上的工作总时差均为零",{"id":451,"libraryId":5,"type":15,"typeLabel":16,"stem":452,"options":453,"answer":20,"analysis":33},1118669,"在某工程网络计划中，工作M的最早开始时间为第7天，其持续时间为5d。工作M工段有三项紧后工作，它们的最早开始时间分别为第15天、第16天和第18天，则工作M的自由时差为()d。",[454,455,456,457],{"key":20,"text":101,"correct":22},{"key":24,"text":154,"correct":26},{"key":28,"text":156,"correct":26},{"key":31,"text":275,"correct":26},{"id":459,"libraryId":5,"type":15,"typeLabel":16,"stem":460,"options":461,"answer":31,"analysis":33},1118670,"在工程网络计划中，某项工作的最迟开始时间与最早开始时间的差值为该工作的()。",[462,464,466,467],{"key":20,"text":463,"correct":26},"时间间隔",{"key":24,"text":465,"correct":26},"搭按时距",{"key":28,"text":69,"correct":26},{"key":31,"text":67,"correct":22},{"id":469,"libraryId":5,"type":15,"typeLabel":16,"stem":470,"options":471,"answer":28,"analysis":33},1118671,"网络计划中某工作自由时差为8，总时差为10，该工作延误9天，问下列的说法正确的是（）。",[472,474,476,478],{"key":20,"text":473,"correct":26},"不会影响紧后工作，也不会影响总工期",{"key":24,"text":475,"correct":26},"不会影响紧后工作，但会影响总工期",{"key":28,"text":477,"correct":22},"会影响紧后工作，但不会影响总工期",{"key":31,"text":479,"correct":26},"会影响紧后工作，也会影响总工期",{"id":481,"libraryId":5,"type":15,"typeLabel":16,"stem":482,"options":483,"answer":31,"analysis":33},1118672,"下图为某办公楼双代号网络计划，其工期为()天。",[484,485,486,487],{"key":20,"text":269,"correct":26},{"key":24,"text":123,"correct":26},{"key":28,"text":279,"correct":26},{"key":31,"text":437,"correct":22},{"id":489,"libraryId":5,"type":15,"typeLabel":16,"stem":490,"options":491,"answer":24,"analysis":33},1118673,"已知单代号网络计划中某工作最早开始时间和最早完成时间分别为4天和6天，最迟开始时间和最迟完成时间分别为7天和9天，则该工作的总时差为()。",[492,494,496,498],{"key":20,"text":493,"correct":26},"2天",{"key":24,"text":495,"correct":22},"3天",{"key":28,"text":497,"correct":26},"4天",{"key":31,"text":163,"correct":26},{"id":500,"libraryId":5,"type":15,"typeLabel":16,"stem":501,"options":502,"answer":24,"analysis":33},1118674,"工程网络计划中,工作E有两项紧后工作G和H,已知工作G和工作H的最早开始时间分别为25和28,工作E的最早开始时间和持续时间分别为17和6,则工作E的自由时差为()。",[503,504,505,506],{"key":20,"text":377,"correct":26},{"key":24,"text":99,"correct":22},{"key":28,"text":101,"correct":26},{"key":31,"text":105,"correct":26},{"id":508,"libraryId":5,"type":15,"typeLabel":16,"stem":509,"options":510,"answer":20,"analysis":33},1118675,"某双代号网络计划中(以天为单位)，工作K的最早开始时间为6.工作持续时间为4；工作M的最迟完成时间为22，工作持续时间为10；工作N的最迟完成时间为20，工作持续时间为5。已知工作K只有M、N两项紧后工作，工作K的总时差为()天。",[511,512,513,514],{"key":20,"text":99,"correct":22},{"key":24,"text":101,"correct":26},{"key":28,"text":105,"correct":26},{"key":31,"text":154,"correct":26},{"id":516,"libraryId":5,"type":15,"typeLabel":16,"stem":517,"options":518,"answer":31,"analysis":33},1118676,"已知单代号网络计划中，工作A最早开始时间(ES)和最早完成时间(E F)分别为10天和24天，则其紧后工作B的最早开始时间(ES2)和最早完成时间（EF2）分别为()。",[519,521,523,525],{"key":20,"text":520,"correct":26},"10天和18天",{"key":24,"text":522,"correct":26},"18天和32天",{"key":28,"text":524,"correct":26},"18天和24天",{"key":31,"text":526,"correct":22},"24天和32天",{"id":528,"libraryId":5,"type":15,"typeLabel":16,"stem":529,"options":530,"answer":20,"analysis":33},1118677,"下列关于单代号网络图与双代号网络图特点的说法，错误的是()。",[531,533,535,537],{"key":20,"text":532,"correct":22},"两种网络图中工作都可以用虚箭头表示",{"key":24,"text":534,"correct":26},"单代号网络图中不使用虚箭头和虚工作",{"key":28,"text":536,"correct":26},"双代号网络图的持续时间不是表示在节点之中的",{"key":31,"text":538,"correct":26},"单代号网络图工作之间的逻辑关系会产生更多的纵横交叉现象",{"id":540,"libraryId":5,"type":15,"typeLabel":16,"stem":541,"options":542,"answer":28,"analysis":33},1118678,"单代号网络图与双代号网络图相比，所具有的特点是( )。",[543,545,547,549],{"key":20,"text":544,"correct":26},"工作间的逻辑关系用虚线，所以绘图较复杂",{"key":24,"text":546,"correct":26},"工作之间的逻辑关系不易表达",{"key":28,"text":548,"correct":22},"由于工作持续时间表示在节点之中，没有长度，故不够形象直观",{"key":31,"text":550,"correct":26},"网络图不便于检查和修改",{"id":552,"libraryId":5,"type":15,"typeLabel":16,"stem":553,"options":554,"answer":31,"analysis":33},1118679,"单代号网络计划中，( )。",[555,557,559,561],{"key":20,"text":556,"correct":26},"箭线表示工作及其进行的方向，节点表示工作之间的逻辑关系",{"key":24,"text":558,"correct":26},"节点表示工作，箭线表示工作进行的方向",{"key":28,"text":560,"correct":26},"箭线表示工作及其进行的方向，节点表示工作的开始或结束",{"key":31,"text":562,"correct":22},"节点表示工作，箭线表示工作之间的逻辑关系",[564,567,570,573,576,579],{"id":15,"name":565,"category":7,"favorite":566},"领导干部任职前廉政法规知识测试题",92,{"id":568,"name":569,"category":7,"favorite":15},595,"建筑结构与设备",{"id":571,"name":572,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":574,"name":575,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":577,"name":578,"category":7,"favorite":8},534,"BIM工程师",{"id":580,"name":578,"category":7,"favorite":8},535]