[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-789-29":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":613},{"id":5,"name":6,"category":7,"favorite":8},789,"二建建设工程施工管理","建筑工程",0,29,50,2973,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,190,202,214,226,238,250,261,273,285,297,309,321,333,345,357,368,380,392,404,416,428,440,452,464,476,488,500,512,524,536,548,558,570,581,591,603],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":24,"analysis":33},1118477,1,"单选题","下列关于施工成本分析依据的说法中正确的是（）。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","会计核算主要是成本核算",false,{"key":24,"text":25,"correct":26},"B","业务核算是对个别的经济业务进行单项核算",true,{"key":28,"text":29,"correct":22},"C","统计核算必须对企业的全部经济活动做出完整、全面、时序的反映",{"key":31,"text":32,"correct":22},"D","业务核算具有连续性、系统性、综合性的特点","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":31,"analysis":33},1118478,"施工项目经理部定的某分部分项工程成本计划，属于（）成本计划",[38,40,42,44],{"key":20,"text":39,"correct":22},"战略性",{"key":24,"text":41,"correct":22},"竞争性",{"key":28,"text":43,"correct":22},"指导性",{"key":31,"text":45,"correct":26},"实施性",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":31,"analysis":33},1118479,"在施工成本分析的依据中，对经济活动进行核算范围最广的是()。",[50,52,54,56],{"key":20,"text":51,"correct":22},"会计核算",{"key":24,"text":53,"correct":22},"成本核算",{"key":28,"text":55,"correct":22},"统计核算",{"key":31,"text":57,"correct":26},"业务核算",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":31,"analysis":33},1118480,"某工程商品混凝土目标产量为500m3，单价为720元\u002Fm3，损耗率为4%，实际产量为580m3，单价为730元\u002Fm3，损耗率为3%，采用因素分析法进行分析，由于单价提高使成本增加了()元",[62,64,66,68],{"key":20,"text":63,"correct":22},"380120",{"key":24,"text":65,"correct":22},"5200",{"key":28,"text":67,"correct":22},"5720",{"key":31,"text":69,"correct":26},"6032",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":20,"analysis":33},1118481,"下列建设工程项目进度控制的措施中，属于技术措施的是()。",[74,76,78,80],{"key":20,"text":75,"correct":26},"优选工程项目施工方案",{"key":24,"text":77,"correct":22},"确定各类进度计划的审批程序",{"key":28,"text":79,"correct":22},"选择合理的合同结构",{"key":31,"text":81,"correct":22},"选择工程承包发包模式",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":20,"analysis":33},1118482,"下列施工成本分析方法中，可以用来分析各种因素对成本影响程度的是()。",[86,88,90,92],{"key":20,"text":87,"correct":26},"连环置换法",{"key":24,"text":89,"correct":22},"相关比率法",{"key":28,"text":91,"correct":22},"比重分析法",{"key":31,"text":93,"correct":22},"动态比率法",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":31,"analysis":33},1118483,"某混凝土搅拌机的台班产量为800m3，与之配合的工人小组有4人，则人工定额为()。",[98,100,102,104],{"key":20,"text":99,"correct":22},"0.2工日\u002Fm3",{"key":24,"text":101,"correct":22},"0.5工日\u002Fm3",{"key":28,"text":103,"correct":22},"0.2工日\u002F100m3",{"key":31,"text":105,"correct":26},"0.5工日\u002F100m3",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":20,"analysis":33},1118484,"建筑安装工程费用中，不能作为竞争性费用的是（）",[110,112,114,116],{"key":20,"text":111,"correct":26},"规费和税金",{"key":24,"text":113,"correct":22},"分部分项工程费",{"key":28,"text":115,"correct":22},"措施项目费",{"key":31,"text":117,"correct":22},"其他项目费",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":20,"analysis":33},1118485,"根据《建筑安装工程费用项目组成》(44号文)，施工企业发生的下列费用中，应计入企业管理费的是()。",[122,124,126,128],{"key":20,"text":123,"correct":26},"劳动保险费",{"key":24,"text":125,"correct":22},"医疗保险费",{"key":28,"text":127,"correct":22},"住房公积金",{"key":31,"text":129,"correct":22},"养老保险费",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":28,"analysis":33},1118486,"某项目编制施工成本计划时，先将成本按分部分项工程进行了划分，又根据施工实施阶段计划将各分部分项工程成本按月汇总进行编制，形成各月成本支出计划，这种编制方法属于()。 A.按施工成本组成编制施工成本计划",[134,136,138,140],{"key":20,"text":135,"correct":22},"按子项目组成编制施工成本计划",{"key":24,"text":137,"correct":22},"按工程实施阶段编制施工成本计划",{"key":28,"text":139,"correct":26},"上述",{"key":31,"text":141,"correct":22},"B两种方法的综合运用",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":28,"analysis":33},1118487,"根据现行《建筑安装工程费用项目组成》（建标[2013]44号），下列费用中，应计入分部分项工程费的是()。",[146,148,150,152],{"key":20,"text":147,"correct":22},"安全文明施工费",{"key":24,"text":149,"correct":22},"二次搬运费",{"key":28,"text":151,"correct":26},"施工机械使用费",{"key":31,"text":153,"correct":22},"大型机械设备进出场及安拆费",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":24,"analysis":33},1118488,"建设工程项目施工成本控制应贯穿于项目从()开始直到()的全过程。",[158,160,162,164],{"key":20,"text":159,"correct":22},"招标阶段，竣工验收",{"key":24,"text":161,"correct":26},"投标阶段，保证金返还",{"key":28,"text":163,"correct":22},"招标阶段，保修期结束",{"key":31,"text":165,"correct":22},"投标阶段，保修期结束",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":24,"analysis":33},1118489,"某工程合同价款是1500万元，其中主要材料金额占合同价款的60%，2004年1月签订合同时，该主要材料综合价格指数为102%。2005年结算时，综合价格指数为115%，则该主要材料结算款需训整的价格差额为()万元。",[170,172,174,176],{"key":20,"text":171,"correct":22},"630.00",{"key":24,"text":173,"correct":26},"114.71",{"key":28,"text":175,"correct":22},"135.00",{"key":31,"text":177,"correct":22},"18.00",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":31,"analysis":33},1118490,"某工程项目有4800m3的土方开挖任务，交由某分包商承担，计划在6个月完成，预算单价为580元\u002Fm3。开工后发现实际单价为600元\u002Fm3。工程进行了3个月，累计完成工程量3000m3.运用赢得值法分析，至第3个月底的进度偏差为（）万元。",[182,184,186,188],{"key":20,"text":183,"correct":22},"-34.8",{"key":24,"text":185,"correct":22},"-6",{"key":28,"text":187,"correct":22},"6",{"key":31,"text":189,"correct":26},"34.8",{"id":191,"libraryId":5,"type":15,"typeLabel":16,"stem":192,"options":193,"answer":31,"analysis":33},1118491,"编制竞争性成本计划的依据，不包括( )。",[194,196,198,200],{"key":20,"text":195,"correct":22},"招标文件中的合同条件",{"key":24,"text":197,"correct":22},"投标者须知",{"key":28,"text":199,"correct":22},"工程量清单",{"key":31,"text":201,"correct":26},"项目实施方案",{"id":203,"libraryId":5,"type":15,"typeLabel":16,"stem":204,"options":205,"answer":20,"analysis":33},1118492,"在施工过程中，暂列金额由建设单位掌握使用，扣除合同价款调整后如有余额，归()。",[206,208,210,212],{"key":20,"text":207,"correct":26},"建设单位",{"key":24,"text":209,"correct":22},"施工单位",{"key":28,"text":211,"correct":22},"监理单位",{"key":31,"text":213,"correct":22},"总承包单位",{"id":215,"libraryId":5,"type":15,"typeLabel":16,"stem":216,"options":217,"answer":20,"analysis":33},1118493,"当发生索赔事件时，对于承包商自有的施工机械，其费用索赔通常按照( )进行计算。",[218,220,222,224],{"key":20,"text":219,"correct":26},"台班折旧费",{"key":24,"text":221,"correct":22},"台班费",{"key":28,"text":223,"correct":22},"设备使用费",{"key":31,"text":225,"correct":22},"进出场费用",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":28,"analysis":33},1118494,"关于编制施工项目成本计划时考虑预备费的说法，正确的是()。",[230,232,234,236],{"key":20,"text":231,"correct":22},"只针对整个项目考虑总的预备费，以便灵活调用",{"key":24,"text":233,"correct":22},"在分析各分项工程风险基础上，只针对部分分项工程考虑预备费",{"key":28,"text":235,"correct":26},"既要针对项目考虑总的预备费，也要在分项工程中安排适当的不可预见费",{"key":31,"text":237,"correct":22},"不考虑整个项目预备费，由施工企业统一考虑",{"id":239,"libraryId":5,"type":15,"typeLabel":16,"stem":240,"options":241,"answer":31,"analysis":33},1118495,"根据《建设工程工程量清单计价规范》(GB50500-2013),关于投标价编制原则说法正确的是()。",[242,244,246,248],{"key":20,"text":243,"correct":22},"投标报价只能由投标人自行编制",{"key":24,"text":245,"correct":22},"投标报价可以另行设定情况优惠总价",{"key":28,"text":247,"correct":22},"投标报价高于招标控制价的必须下调后采用",{"key":31,"text":249,"correct":26},"投标报价不得低于工程成本",{"id":251,"libraryId":5,"type":15,"typeLabel":16,"stem":252,"options":253,"answer":28,"analysis":33},1118496,"某施工企业为施工生产提供预付款担保、履约担保发生的各种费用属于（ ）。",[254,256,258,260],{"key":20,"text":255,"correct":22},"办公费",{"key":24,"text":257,"correct":22},"投标费",{"key":28,"text":259,"correct":26},"财务费",{"key":31,"text":117,"correct":22},{"id":262,"libraryId":5,"type":15,"typeLabel":16,"stem":263,"options":264,"answer":31,"analysis":33},1118497,"某施工项目分部分项工程费为1200万元，其中人工费为450万元，机械费为300万元，可计量的措施项目费为400万元，该施工项目的安全文明施工费以人工费和机械费为计算基础，费率为2%，则该施工项目的安全文明施工费为（ ）万元。",[265,267,269,271],{"key":20,"text":266,"correct":22},"32",{"key":24,"text":268,"correct":22},"24",{"key":28,"text":270,"correct":22},"23",{"key":31,"text":272,"correct":26},"15",{"id":274,"libraryId":5,"type":15,"typeLabel":16,"stem":275,"options":276,"answer":20,"analysis":33},1118498,"某施工企业的企业管理费费率以人工费为计算基础，其生产工人年平均管理费为4500元，年有效施工天数为300天，人工单价为80元\u002F天，人工费占分部分项工程费的比例为25%，则该企业的企业管理费费率为（ ）。",[277,279,281,283],{"key":20,"text":278,"correct":26},"18.75%",{"key":24,"text":280,"correct":22},"17.78",{"key":28,"text":282,"correct":22},"15%",{"key":31,"text":284,"correct":22},"4.69",{"id":286,"libraryId":5,"type":15,"typeLabel":16,"stem":287,"options":288,"answer":20,"analysis":33},1118499,"某独立土方工程，招标文件中估计工程量为200万m3，合同中规定：土方工程单价为8元\u002Fm3，当实际工程量超过估计工程量15%时，调整单价，单价调为6元\u002Fm3。工程结束时实际完成土方工程量为250万m3，则土方工程款为（）万元。",[289,291,293,295],{"key":20,"text":290,"correct":26},"1960",{"key":24,"text":292,"correct":22},"1600",{"key":28,"text":294,"correct":22},"1200",{"key":31,"text":296,"correct":22},"1900",{"id":298,"libraryId":5,"type":15,"typeLabel":16,"stem":299,"options":300,"answer":28,"analysis":33},1118500,"下列关于费用（进度）偏差和费用（进度）绩效指数的说法，正确的是()。",[301,303,305,307],{"key":20,"text":302,"correct":22},"费用（进度）偏差反映的是相对偏差",{"key":24,"text":304,"correct":22},"费用（进度）绩效指数反映的是绝对偏差",{"key":28,"text":306,"correct":26},"费用（进度）偏差仅适合于对同一项目作偏差分析",{"key":31,"text":308,"correct":22},"费用（进度）绩效指数受项目层次和项目实施时间的限制",{"id":310,"libraryId":5,"type":15,"typeLabel":16,"stem":311,"options":312,"answer":31,"analysis":33},1118501,"建设工程项目总进度目标的控制是（ ）项目管理的任务之一。",[313,315,317,319],{"key":20,"text":314,"correct":22},"施工总承包方",{"key":24,"text":316,"correct":22},"设计方",{"key":28,"text":318,"correct":22},"施工方和设计方",{"key":31,"text":320,"correct":26},"业主方",{"id":322,"libraryId":5,"type":15,"typeLabel":16,"stem":323,"options":324,"answer":28,"analysis":33},1118502,"育才中学的教学楼工程由甲设计院设计，由乙建筑公司进行施工总承包，则教学楼建设工程项目实施阶段的总进度目标控制应当由( )来进行。",[325,327,329,331],{"key":20,"text":326,"correct":22},"甲设计院",{"key":24,"text":328,"correct":22},"乙建筑公司",{"key":28,"text":330,"correct":26},"育才中学",{"key":31,"text":332,"correct":22},"项目经理",{"id":334,"libraryId":5,"type":15,"typeLabel":16,"stem":335,"options":336,"answer":20,"analysis":33},1118503,"建设工程项目的总进度目标是在项目的()阶段确定的。",[337,339,341,343],{"key":20,"text":338,"correct":26},"决策",{"key":24,"text":340,"correct":22},"设计",{"key":28,"text":342,"correct":22},"招标",{"key":31,"text":344,"correct":22},"施工",{"id":346,"libraryId":5,"type":15,"typeLabel":16,"stem":347,"options":348,"answer":31,"analysis":33},1118504,"建设工程项目的总进度目标指的是整个项目的进度目标，它是在()阶段项目定义时确定的。",[349,351,353,355],{"key":20,"text":350,"correct":22},"项目审批",{"key":24,"text":352,"correct":22},"项目实施",{"key":28,"text":354,"correct":22},"项目定义",{"key":31,"text":356,"correct":26},"项目决策",{"id":358,"libraryId":5,"type":15,"typeLabel":16,"stem":359,"options":360,"answer":20,"analysis":33},1118505,"对于采用建设项目总承包模式的建设工程，项目总进度目标的控制是()的任务。",[361,363,365,366],{"key":20,"text":362,"correct":26},"业主",{"key":24,"text":364,"correct":22},"总承包方",{"key":28,"text":316,"correct":22},{"key":31,"text":367,"correct":22},"监理方",{"id":369,"libraryId":5,"type":15,"typeLabel":16,"stem":370,"options":371,"answer":24,"analysis":33},1118506,"施工进度控制不仅关系到施工进度目标能否实现，它还直接关系到工程的质量和( )。",[372,374,376,378],{"key":20,"text":373,"correct":22},"工期",{"key":24,"text":375,"correct":26},"成本",{"key":28,"text":377,"correct":22},"投资",{"key":31,"text":379,"correct":22},"安全",{"id":381,"libraryId":5,"type":15,"typeLabel":16,"stem":382,"options":383,"answer":20,"analysis":33},1118507,"在项目施工实践中，必须树立和坚持一个最基本的工程管理原则，即在（）的前提下，控制工程的进度。",[384,386,388,390],{"key":20,"text":385,"correct":26},"确保工程质量",{"key":24,"text":387,"correct":22},"确保经济效益",{"key":28,"text":389,"correct":22},"确保施工进度计划",{"key":31,"text":391,"correct":22},"确保投资限额",{"id":393,"libraryId":5,"type":15,"typeLabel":16,"stem":394,"options":395,"answer":28,"analysis":33},1118508,"在工程施工实践中，必须树立和坚持一个最基本的工程管理原则是（）。",[396,398,400,402],{"key":20,"text":397,"correct":22},"在确保工程进度的前提下，控制工程的投资",{"key":24,"text":399,"correct":22},"在确保工程投资的前提下，控制工程的质量",{"key":28,"text":401,"correct":26},"在确保工程质量的前提下，控制工程的进度",{"key":31,"text":403,"correct":22},"在不影响工程质量的前提下，最大限度地满足业主方的需求",{"id":405,"libraryId":5,"type":15,"typeLabel":16,"stem":406,"options":407,"answer":31,"analysis":33},1118509,"在进行建设工程项目总进度目标控制前，首先应该()。",[408,410,412,414],{"key":20,"text":409,"correct":22},"分析项目的合同结构",{"key":24,"text":411,"correct":22},"编制详细的网络计划",{"key":28,"text":413,"correct":22},"分析项目资金流量",{"key":31,"text":415,"correct":26},"分析进度目标实现的可能性",{"id":417,"libraryId":5,"type":15,"typeLabel":16,"stem":418,"options":419,"answer":24,"analysis":33},1118510,"建设工程项目的总进度目标指的是整个项目的进度目标，在进行建设工程项目总进度目标控制前，首先应（）。",[420,422,424,426],{"key":20,"text":421,"correct":22},"制定总进度目标",{"key":24,"text":423,"correct":26},"分析和论证目标实现的可能性",{"key":28,"text":425,"correct":22},"论证总进度纲要",{"key":31,"text":427,"correct":22},"确定里程碑事件及进度计划与目标",{"id":429,"libraryId":5,"type":15,"typeLabel":16,"stem":430,"options":431,"answer":31,"analysis":33},1118511,"在项目的实施阶段，关于项目总进度和施工进度的说法正确的是( )",[432,434,436,438],{"key":20,"text":433,"correct":22},"项目总进度主要是施工进度",{"key":24,"text":435,"correct":22},"项目总进度主要包括设计、施工进度",{"key":28,"text":437,"correct":22},"项目总进度包括设计、施工前准备、工程施工和设备安装、工程物资采购等工作进度",{"key":31,"text":439,"correct":26},"项目总进度包括设计前准备阶段、设计、招标、施工前准备，工程施工和设备安装、工程物资采购，项目动用前准备等工作进度",{"id":441,"libraryId":5,"type":15,"typeLabel":16,"stem":442,"options":443,"answer":20,"analysis":33},1118512,"在进行建设工程项目总进度目标控制前，首先应分析和论证( )。",[444,446,448,450],{"key":20,"text":445,"correct":26},"目标实现的可能性",{"key":24,"text":447,"correct":22},"目标计划的可行性",{"key":28,"text":449,"correct":22},"目标完成的收益情况",{"key":31,"text":451,"correct":22},"目标实施的步骤",{"id":453,"libraryId":5,"type":15,"typeLabel":16,"stem":454,"options":455,"answer":24,"analysis":33},1118513,"项目进度控制的主要工作环节中，首先应进行的工作是()。",[456,458,460,462],{"key":20,"text":457,"correct":22},"编制进度计划",{"key":24,"text":459,"correct":26},"分析和论证进度目标",{"key":28,"text":461,"correct":22},"定期跟踪进度计划的执行情况",{"key":31,"text":463,"correct":22},"采取纠偏措施",{"id":465,"libraryId":5,"type":15,"typeLabel":16,"stem":466,"options":467,"answer":28,"analysis":33},1118514,"下列关于工程进度、质量、成本安全之间的关系及其管理工作的说法中，正确的是（）。",[468,470,472,474],{"key":20,"text":469,"correct":22},"工程进度控制与工程质量、成本无关",{"key":24,"text":471,"correct":22},"赶工会导致工程质量和安全问题出现，但会降低工程成本",{"key":28,"text":473,"correct":26},"缩短工期要以确保工程质量、安全为前提",{"key":31,"text":475,"correct":22},"只要赶工所增加的成本可以承受，就应尽量缩短工期",{"id":477,"libraryId":5,"type":15,"typeLabel":16,"stem":478,"options":479,"answer":31,"analysis":33},1118515,"建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，它在()。",[480,482,484,486],{"key":20,"text":481,"correct":22},"项目立项时建立",{"key":24,"text":483,"correct":22},"项目设计前准备阶段建立",{"key":28,"text":485,"correct":22},"项目施工前准备阶段建立",{"key":31,"text":487,"correct":26},"项目进展过程中逐步完善",{"id":489,"libraryId":5,"type":15,"typeLabel":16,"stem":490,"options":491,"answer":24,"analysis":33},1118516,"施工单位控制施工工作进度的依据是( )。",[492,494,496,498],{"key":20,"text":493,"correct":22},"业主方缩短工期的要求",{"key":24,"text":495,"correct":26},"施工承包合同对工期的要求",{"key":28,"text":497,"correct":22},"建筑工程工期定额",{"key":31,"text":499,"correct":22},"同类工程最短工期的记录",{"id":501,"libraryId":5,"type":15,"typeLabel":16,"stem":502,"options":503,"answer":28,"analysis":33},1118517,"建设工程项目总进度目标论证中，进度计划系统的结构分析之后的工作是（）。",[504,506,508,510],{"key":20,"text":505,"correct":22},"编制各层进度计划",{"key":24,"text":507,"correct":22},"项目结构分析",{"key":28,"text":509,"correct":26},"项目的工作编码",{"key":31,"text":511,"correct":22},"调查研究和收集资料",{"id":513,"libraryId":5,"type":15,"typeLabel":16,"stem":514,"options":515,"answer":28,"analysis":33},1118518,"大型建设工程项目总进度论证的核心工作是( )。",[516,518,520,522],{"key":20,"text":517,"correct":22},"明确进度控制的措施",{"key":24,"text":519,"correct":22},"分析影响施工进度且目标实现的主要因素",{"key":28,"text":521,"correct":26},"通过编制总进度纲要论证总进度目标实现的可能性",{"key":31,"text":523,"correct":22},"编制各层（各级）进度计划",{"id":525,"libraryId":5,"type":15,"typeLabel":16,"stem":526,"options":527,"answer":31,"analysis":33},1118519,"建设工程项目实施阶段策划的工作内容中，属于项目目标的分析和再论证内容的是（）。",[528,530,532,534],{"key":20,"text":529,"correct":22},"项目风险管理与工程保险方案",{"key":24,"text":531,"correct":22},"项目管理工作流程",{"key":28,"text":533,"correct":22},"关键技术的深化分析和论证",{"key":31,"text":535,"correct":26},"编制项目建设总进度规划",{"id":537,"libraryId":5,"type":15,"typeLabel":16,"stem":538,"options":539,"answer":28,"analysis":33},1118520,"大型建设工程项目总进度目标论证的核心工作是通过（ ）论证进度目标实现的可能性。",[540,542,544,546],{"key":20,"text":541,"correct":22},"指导进度规划",{"key":24,"text":543,"correct":22},"拟订工程项目总进度计划",{"key":28,"text":545,"correct":26},"编制总进度纲要",{"key":31,"text":547,"correct":22},"绘制工程项目进度平衡表",{"id":549,"libraryId":5,"type":15,"typeLabel":16,"stem":550,"options":551,"answer":24,"analysis":33},1118521,"建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，这是（ ）的依据。",[552,553,555,556],{"key":20,"text":352,"correct":22},{"key":24,"text":554,"correct":26},"项目进度控制",{"key":28,"text":545,"correct":22},{"key":31,"text":557,"correct":22},"进行项目结构分析",{"id":559,"libraryId":5,"type":15,"typeLabel":16,"stem":560,"options":561,"answer":28,"analysis":33},1118522,"作为建设工程项目进度控制的依据，建设工程项目进度计划系统应()。",[562,564,566,568],{"key":20,"text":563,"correct":22},"在项目的前期决策阶段建立",{"key":24,"text":565,"correct":22},"在项目的初步设计阶段完善",{"key":28,"text":567,"correct":26},"在项目的进展过程中逐步形成",{"key":31,"text":569,"correct":22},"在项目的施工准备阶段立",{"id":571,"libraryId":5,"type":15,"typeLabel":16,"stem":572,"options":573,"answer":31,"analysis":33},1118523,"某省拟新建一所综合性大学，项目建设单位组织有关专家对该项目的总进度目标进行论证，编制完各层进度计划后，紧接着应进行的工作是()。",[574,575,577,579],{"key":20,"text":557,"correct":22},{"key":24,"text":576,"correct":22},"进行进度计划系统的结构分析",{"key":28,"text":578,"correct":22},"确定项目的工作编码",{"key":31,"text":580,"correct":26},"协调各层进度计划的关系和编制总进度计划",{"id":582,"libraryId":5,"type":15,"typeLabel":16,"stem":583,"options":584,"answer":24,"analysis":33},1118524,"根据建设工程项目总进度目标论证的工作步骤，在完成“项目结构分析”工作之后立即进行的工作是()。",[585,587,589,590],{"key":20,"text":586,"correct":22},"调查研究和搜集资料",{"key":24,"text":588,"correct":26},"进度计划系统的结构分析",{"key":28,"text":509,"correct":22},{"key":31,"text":505,"correct":22},{"id":592,"libraryId":5,"type":15,"typeLabel":16,"stem":593,"options":594,"answer":20,"analysis":33},1118525,"建设工程项目总进度目标论证的工作有：①项目的工作编码；②项目结构分析；③编制各层进度计划；④进度计划系统的结构分析等。对上述四项工作而言，其正确的工作步骤是（ ）。",[595,597,599,601],{"key":20,"text":596,"correct":26},"②→④→①→③",{"key":24,"text":598,"correct":22},"①→②→④→③",{"key":28,"text":600,"correct":22},"①→③→④→②",{"key":31,"text":602,"correct":22},"②→④→③→①",{"id":604,"libraryId":5,"type":15,"typeLabel":16,"stem":605,"options":606,"answer":24,"analysis":33},1118526,"某新建的大型会展中心，项目建设单位组织专家对该项目的总进度目标进行论证，在进行进度计划系统的结构分析后，紧接着应进行的工作是()。",[607,609,611,612],{"key":20,"text":608,"correct":22},"编制总进度计划",{"key":24,"text":610,"correct":26},"确定项目工作编码",{"key":28,"text":505,"correct":22},{"key":31,"text":557,"correct":22},[614,617,620,623,626,629],{"id":15,"name":615,"category":7,"favorite":616},"领导干部任职前廉政法规知识测试题",92,{"id":618,"name":619,"category":7,"favorite":15},595,"建筑结构与设备",{"id":621,"name":622,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":624,"name":625,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":627,"name":628,"category":7,"favorite":8},534,"BIM工程师",{"id":630,"name":628,"category":7,"favorite":8},535]