[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-789-20":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":592},{"id":5,"name":6,"category":7,"favorite":8},789,"二建建设工程施工管理","建筑工程",0,20,50,2973,[13,34,46,58,70,82,94,106,118,130,142,154,164,176,188,200,212,224,236,248,260,272,284,296,308,320,329,338,347,359,371,383,395,403,415,427,437,449,459,471,483,493,505,517,525,537,548,560,572,584],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":27,"analysis":33},1118024,1,"单选题","某施工企业按规定为职工购买防暑降温饮料的支出属于( )。",[19,23,26,30],{"key":20,"text":21,"correct":22},"A","人工费里的补贴",false,{"key":24,"text":25,"correct":22},"B","职工福利费",{"key":27,"text":28,"correct":29},"C","劳动保护费",true,{"key":31,"text":32,"correct":22},"D","企业管理费中的其他费用","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":27,"analysis":33},1118025,"某施工机械预算价格为150万元，折旧年限为10年，残值率为5%，年平均工作250班，则该施工机械台班折旧费为()元。",[38,40,42,44],{"key":20,"text":39,"correct":22},"460",{"key":24,"text":41,"correct":22},"490",{"key":27,"text":43,"correct":29},"570",{"key":31,"text":45,"correct":22},"590",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":20,"analysis":33},1118026,"某施工机械预算价格为100万元，折旧年限为10年，年平均工作250个台班，一次大修理费用为25万元，大修理次数为3次，则该机械台班大修理费为( )元。",[50,52,54,56],{"key":20,"text":51,"correct":29},"300",{"key":24,"text":53,"correct":22},"320",{"key":27,"text":55,"correct":22},"330",{"key":31,"text":57,"correct":22},"350",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":24,"analysis":33},1118027,"根据我国现行建筑安装工程费用项目组成的规定，下列有关费用的表述中不正确的是()。",[62,64,66,68],{"key":20,"text":63,"correct":22},"施工机具使用费包含仪器仪表使用费",{"key":24,"text":65,"correct":29},"材料费包含构成或计划构成永久工程一部分的工程设备费",{"key":27,"text":67,"correct":22},"材料费中的材料单价由材料原价、材料运杂费、材料损耗费、采购及保管费五项组成",{"key":31,"text":69,"correct":22},"人工费是指支付给直接从事建筑安装工程施工的生产工人和附属生产单位工人的各项费用",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":24,"analysis":33},1118028,"某施工机械预算价格为40万元，估计残值率为3%，折旧年限为10年，年工作台班数为250台班，则该机械的台班折旧费为()元。",[74,76,78,80],{"key":20,"text":75,"correct":22},"19.59",{"key":24,"text":77,"correct":29},"155.20",{"key":27,"text":79,"correct":22},"160.00",{"key":31,"text":81,"correct":22},"164.80",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":31,"analysis":33},1118029,"根据《建筑安装工程费用项目组成》（44号文），材料费是指施工过程中耗用的构成工程实体的原材料、辅助材料、构配件、零件、半成品的费用，其价格是指()。",[86,88,90,92],{"key":20,"text":87,"correct":22},"由材料供应厂商运到工地仓库的价格",{"key":24,"text":89,"correct":22},"材料的出厂价格",{"key":27,"text":91,"correct":22},"由材料供应厂商运到工地仓库经过检验试验和保管后的出库价格",{"key":31,"text":93,"correct":29},"由材料原价、材料运杂费、运输损耗费、采购及保管费的构成",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":24,"analysis":33},1118030,"我国现行建筑安装工程定额规定，企业支付给离退休职工的退休金应计入( )。",[98,100,102,104],{"key":20,"text":99,"correct":22},"生产工人工资",{"key":24,"text":101,"correct":29},"劳动保险费",{"key":27,"text":103,"correct":22},"职工待业保险费",{"key":31,"text":105,"correct":22},"企业其他费用",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":24,"analysis":33},1118031,"某施工工程人工费为80万元，材料费为140万元，施工机具使用费为40万元，企业管理费以人工费和机械费合计为计算基础，费率为18%，利润率以人工费为计算基础，费率为30%，规费30万元，综合计税系数为3.41%，则该工程的含税造价为( )万元。",[110,112,114,116],{"key":20,"text":111,"correct":22},"316",{"key":24,"text":113,"correct":29},"347",{"key":27,"text":115,"correct":22},"360",{"key":31,"text":117,"correct":22},"50",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":31,"analysis":33},1118032,"总承包人为配合、协调建设单位进行的专业工程发包，对建设单位自行采购的材料、工程设备等进行保管以及施工现场管理、竣工资料汇总整理等服务所需的费用属于( )。",[122,124,126,128],{"key":20,"text":123,"correct":22},"计日工",{"key":24,"text":125,"correct":22},"暂估价",{"key":27,"text":127,"correct":22},"暂列金额",{"key":31,"text":129,"correct":29},"总承包服务费",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":31,"analysis":33},1118033,"下列费用中不属于施工机具使用费的是（ ）。",[134,136,138,140],{"key":20,"text":135,"correct":22},"施工机械在规定年限内的折旧费",{"key":24,"text":137,"correct":22},"施工机械必要的大修理费",{"key":27,"text":139,"correct":22},"施工机械的各级保养和临时故障排除所需的费用",{"key":31,"text":141,"correct":29},"大型施工机械在现场进行安装与拆卸的费用",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":27,"analysis":33},1118034,"某施工企业投标报价时确定企业管理费率以人工费为基础计算，据统计资料，该施工企业生产工人年平均管理费为1.2万元，年有效施工天数为240天，人工单价为300元\u002F天，人工费占分部分项工程费的比例为75%，则该企业的企业管理费费率应为（）。",[146,148,150,152],{"key":20,"text":147,"correct":22},"12.15%",{"key":24,"text":149,"correct":22},"12.5%",{"key":27,"text":151,"correct":29},"16.67%",{"key":31,"text":153,"correct":22},"22.22%",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":27,"analysis":33},1118035,"根据《建筑安装工程费用项目组成》（44号文），下列费用中属于规费的是（）。",[158,159,160,162],{"key":20,"text":101,"correct":22},{"key":24,"text":28,"correct":22},{"key":27,"text":161,"correct":29},"工伤保险费",{"key":31,"text":163,"correct":22},"意外伤害险费",{"id":165,"libraryId":5,"type":15,"typeLabel":16,"stem":166,"options":167,"answer":27,"analysis":33},1118036,"按造价形成划分，建筑安装工程费由（ ）组成。",[168,170,172,174],{"key":20,"text":169,"correct":22},"人工费+材料费+施工机具使用费+措施项目费+规费+税金",{"key":24,"text":171,"correct":22},"人工费+材料费+施工机具使用费+其他项目费+规费+税金",{"key":27,"text":173,"correct":29},"分部分项工程费+措施项目费+其他项目费+规费+税金",{"key":31,"text":175,"correct":22},"分部分项工程费+施工机具使用费+其他项目费+规费+税金",{"id":177,"libraryId":5,"type":15,"typeLabel":16,"stem":178,"options":179,"answer":20,"analysis":33},1118037,"在建筑安装工程费的构成中，税金是指国家税法规定的应计入建筑安装工程造价内的()。",[180,182,184,186],{"key":20,"text":181,"correct":29},"增值税9%",{"key":24,"text":183,"correct":22},"营业税、房产税、车船使用税和土地使用税",{"key":27,"text":185,"correct":22},"房产税、车船使用税、土地使用税和印花税",{"key":31,"text":187,"correct":22},"房产税、土地使用税和营业税",{"id":189,"libraryId":5,"type":15,"typeLabel":16,"stem":190,"options":191,"answer":20,"analysis":33},1118038,"某施工企业的企业管理费费率以人工费为计算基础，其生产工人年平均管理费为4500元，年有效施工天数为300天，人工单价为80元／天，人工费占分部分项工程费的比例为25%，则该企业的企业管理费费率为( )。",[192,194,196,198],{"key":20,"text":193,"correct":29},"18.75%",{"key":24,"text":195,"correct":22},"17.78%",{"key":27,"text":197,"correct":22},"15.00%",{"key":31,"text":199,"correct":22},"4.69%",{"id":201,"libraryId":5,"type":15,"typeLabel":16,"stem":202,"options":203,"answer":31,"analysis":33},1118039,"根据《建筑安装工程费用项目组成》（建标[20031206号），环境保护费属于建筑安装工程费用中的()。",[204,206,208,210],{"key":20,"text":205,"correct":22},"企业管理费",{"key":24,"text":207,"correct":22},"直接工程费",{"key":27,"text":209,"correct":22},"规费",{"key":31,"text":211,"correct":29},"措施费",{"id":213,"libraryId":5,"type":15,"typeLabel":16,"stem":214,"options":215,"answer":20,"analysis":33},1118040,"根据《建筑安装工程费用项目组成》，下列费用中不属于措施项目费的是（）。",[216,218,220,222],{"key":20,"text":217,"correct":29},"检验试验费",{"key":24,"text":219,"correct":22},"环境保护费",{"key":27,"text":221,"correct":22},"工程定位复测费",{"key":31,"text":223,"correct":22},"脚手架工程费",{"id":225,"libraryId":5,"type":15,"typeLabel":16,"stem":226,"options":227,"answer":31,"analysis":33},1118041,"斗容量1立方米正铲挖土机，挖四类土，装车，深度在2m内，小组成员两人，机械台班产量为4.76（定额单位100m3），则挖100m3的人工时间定额为( )工日。",[228,230,232,234],{"key":20,"text":229,"correct":22},"0.21",{"key":24,"text":231,"correct":22},"0.22",{"key":27,"text":233,"correct":22},"0.23",{"key":31,"text":235,"correct":29},"0.42",{"id":237,"libraryId":5,"type":15,"typeLabel":16,"stem":238,"options":239,"answer":24,"analysis":33},1118042,"从性质上看，施工定额是( )。",[240,242,244,246],{"key":20,"text":241,"correct":22},"社会性的定额",{"key":24,"text":243,"correct":29},"企业性的定额",{"key":27,"text":245,"correct":22},"地区性的定额",{"key":31,"text":247,"correct":22},"行业性的定额",{"id":249,"libraryId":5,"type":15,"typeLabel":16,"stem":250,"options":251,"answer":24,"analysis":33},1118043,"编制标准砖砌体的材料消耗定额时，砌筑砂浆的消耗量应按( )确定。",[252,254,256,258],{"key":20,"text":253,"correct":22},"净用量",{"key":24,"text":255,"correct":29},"净用量加损耗量",{"key":27,"text":257,"correct":22},"一次损耗量",{"key":31,"text":259,"correct":22},"损耗量加补损量",{"id":261,"libraryId":5,"type":15,"typeLabel":16,"stem":262,"options":263,"answer":24,"analysis":33},1118044,"编制工程概算定额的基础是( )。",[264,266,268,270],{"key":20,"text":265,"correct":22},"施工定额",{"key":24,"text":267,"correct":29},"预算定额",{"key":27,"text":269,"correct":22},"概算指标",{"key":31,"text":271,"correct":22},"投资估算指标",{"id":273,"libraryId":5,"type":15,"typeLabel":16,"stem":274,"options":275,"answer":27,"analysis":33},1118045,"施工定额是企业性质的定额，可以用来（）",[276,278,280,282],{"key":20,"text":277,"correct":22},"确定工程造价",{"key":24,"text":279,"correct":22},"控制建设工程投资",{"key":27,"text":281,"correct":29},"编制施工作业计划",{"key":31,"text":283,"correct":22},"进行建设项目管理",{"id":285,"libraryId":5,"type":15,"typeLabel":16,"stem":286,"options":287,"answer":27,"analysis":33},1118046,"根据企业的人员素质、机械装备程度、技术和管理水平等情况编制的定额是（ ）。",[288,290,292,294],{"key":20,"text":289,"correct":22},"行业定额",{"key":24,"text":291,"correct":22},"地区定额",{"key":27,"text":293,"correct":29},"企业定额",{"key":31,"text":295,"correct":22},"临时定额",{"id":297,"libraryId":5,"type":15,"typeLabel":16,"stem":298,"options":299,"answer":24,"analysis":33},1118047,"在制定材料消耗定额时，可以用来确定材料损耗率的方法是()。",[300,302,304,306],{"key":20,"text":301,"correct":22},"理论计算法",{"key":24,"text":303,"correct":29},"观察法",{"key":27,"text":305,"correct":22},"经验法",{"key":31,"text":307,"correct":22},"计算法",{"id":309,"libraryId":5,"type":15,"typeLabel":16,"stem":310,"options":311,"answer":31,"analysis":33},1118048,"概算定额一般是在预算定额的基础上综合扩大而成的，这是指()。",[312,314,316,318],{"key":20,"text":313,"correct":22},"概算定额的适用范围比预算定额大",{"key":24,"text":315,"correct":22},"概算定额的子目比预算定额多",{"key":27,"text":317,"correct":22},"概算定额的消耗量比预算定额少",{"key":31,"text":319,"correct":29},"概算定额中的每个综合分项都包含了数项预算定额的子目",{"id":321,"libraryId":5,"type":15,"typeLabel":16,"stem":322,"options":323,"answer":20,"analysis":33},1118049,"在下列定额中，定额水平需要反映施工企业生产与组织的技术水平和管理水平的是()。",[324,325,326,328],{"key":20,"text":265,"correct":29},{"key":24,"text":267,"correct":22},{"key":27,"text":327,"correct":22},"概算定额",{"key":31,"text":269,"correct":22},{"id":330,"libraryId":5,"type":15,"typeLabel":16,"stem":331,"options":332,"answer":20,"analysis":33},1118050,"工程建设定额中分项最细、定额子目最多的一种定额，也是建设工程定额中的基础性定额是()。",[333,334,335,336],{"key":20,"text":265,"correct":29},{"key":24,"text":267,"correct":22},{"key":27,"text":327,"correct":22},{"key":31,"text":337,"correct":22},"建筑工程定额",{"id":339,"libraryId":5,"type":15,"typeLabel":16,"stem":340,"options":341,"answer":24,"analysis":33},1118051,"以施工定额为基础综合扩大编制的，同时也是编制概算定额的基础的是（）。",[342,344,345,346],{"key":20,"text":343,"correct":22},"人工定额",{"key":24,"text":267,"correct":29},{"key":27,"text":269,"correct":22},{"key":31,"text":271,"correct":22},{"id":348,"libraryId":5,"type":15,"typeLabel":16,"stem":349,"options":350,"answer":24,"analysis":33},1118052,"某施工机械的产量定额为2.56(100m3\u002F台班)，与之配合的工人小组有4人，则与该机械配合的人工时间定额为( )工日\u002F100m3。",[351,353,355,357],{"key":20,"text":352,"correct":22},"0.016",{"key":24,"text":354,"correct":29},"1.563",{"key":27,"text":356,"correct":22},"10.24",{"key":31,"text":358,"correct":22},"0.391",{"id":360,"libraryId":5,"type":15,"typeLabel":16,"stem":361,"options":362,"answer":27,"analysis":33},1118053,"关于材料与周转性材料消耗量的说法，正确的是()。",[363,365,367,369],{"key":20,"text":364,"correct":22},"周转性材料的消耗量应当用材料的一次使用量指标表示",{"key":24,"text":366,"correct":22},"材料的消耗量是指材料的净用量",{"key":27,"text":368,"correct":29},"周转性材料的摊销量供施工企业成本核算或投标报价使用",{"key":31,"text":370,"correct":22},"周转性材料的消耗与周转使用次数无关",{"id":372,"libraryId":5,"type":15,"typeLabel":16,"stem":373,"options":374,"answer":24,"analysis":33},1118054,"将定额分为施工定额、预算定额、概算定额、概算指标以及投资估算指标，这是按()对定额进行分类",[375,377,379,381],{"key":20,"text":376,"correct":22},"生产要素",{"key":24,"text":378,"correct":29},"编制程序和用途",{"key":27,"text":380,"correct":22},"编制单位和适用范围",{"key":31,"text":382,"correct":22},"投资的费用性质",{"id":384,"libraryId":5,"type":15,"typeLabel":16,"stem":385,"options":386,"answer":24,"analysis":33},1118055,"关于施工定额的方法，正确的是（）",[387,389,391,393],{"key":20,"text":388,"correct":22},"施工定额是以建筑物或构筑物各个分部分项工程为对象编制的定额",{"key":24,"text":390,"correct":29},"施工定额由人工定额、材料消耗定额、施工机械台班消耗定额组成",{"key":27,"text":392,"correct":22},"施工定额的编制考虑行业工程建设特点、在本行业范围内使用",{"key":31,"text":394,"correct":22},"施工定额由国家建设行政部门组织编制",{"id":396,"libraryId":5,"type":15,"typeLabel":16,"stem":397,"options":398,"answer":31,"analysis":33},1118056,"能够反映施工企业生产与组织的技术水平和管理水平，直接应用于项目施工管理的定额是()。",[399,400,401,402],{"key":20,"text":269,"correct":22},{"key":24,"text":327,"correct":22},{"key":27,"text":267,"correct":22},{"key":31,"text":265,"correct":29},{"id":404,"libraryId":5,"type":15,"typeLabel":16,"stem":405,"options":406,"answer":20,"analysis":33},1118057,"已知某施工工序在合理条件下，工人在单位工日中所完成的合格产品数量为4.56m3，则该工序的人工时间定额为()。",[407,409,411,413],{"key":20,"text":408,"correct":29},"0.22工日",{"key":24,"text":410,"correct":22},"0.22工日\u002Fm3",{"key":27,"text":412,"correct":22},"4.56工日\u002Fm3",{"key":31,"text":414,"correct":22},"1.76m3",{"id":416,"libraryId":5,"type":15,"typeLabel":16,"stem":417,"options":418,"answer":24,"analysis":33},1118058,"关于周转性材料消耗量的说法，正确的是()",[419,421,423,425],{"key":20,"text":420,"correct":22},"周转性材料的损耗一般以损耗率表示",{"key":24,"text":422,"correct":29},"周转性材料的摊销量可以供施工企业投标报价使用",{"key":27,"text":424,"correct":22},"周转性材料的一次使用量供施工企业成本核算使用",{"key":31,"text":426,"correct":22},"周转性材料的消耗与其最终回收折价无关",{"id":428,"libraryId":5,"type":15,"typeLabel":16,"stem":429,"options":430,"answer":20,"analysis":33},1118059,"在正常的施工技术和组织条件下，完成单位合格产品所必需的人工消耗量标准，称为()。",[431,432,434,436],{"key":20,"text":343,"correct":29},{"key":24,"text":433,"correct":22},"材料消耗定额",{"key":27,"text":435,"correct":22},"施工机械台班使用定额",{"key":31,"text":265,"correct":22},{"id":438,"libraryId":5,"type":15,"typeLabel":16,"stem":439,"options":440,"answer":20,"analysis":33},1118060,"施工定额是以()为对象编制的。",[441,443,445,447],{"key":20,"text":442,"correct":29},"同一性质的施工过程——工序",{"key":24,"text":444,"correct":22},"建筑物或构筑物各个分项工程",{"key":27,"text":446,"correct":22},"扩大的分部分项工程",{"key":31,"text":448,"correct":22},"独立的单项工程或完整的工程项目",{"id":450,"libraryId":5,"type":15,"typeLabel":16,"stem":451,"options":452,"answer":24,"analysis":33},1118061,"投资估算指标通常是以()为计算对象编制确定的生产要素消耗的数量标准或项目费用标准。",[453,455,456,457],{"key":20,"text":454,"correct":22},"整个建筑物和构筑物",{"key":24,"text":448,"correct":29},{"key":27,"text":446,"correct":22},{"key":31,"text":458,"correct":22},"建筑物或构筑物各个分部分项工程",{"id":460,"libraryId":5,"type":15,"typeLabel":16,"stem":461,"options":462,"answer":31,"analysis":33},1118062,"若完成某分项工程需要某种材料的净耗量为0.95 t，损耗率为5%，那么，总消耗量为() t。",[463,465,467,469],{"key":20,"text":464,"correct":22},"0.8",{"key":24,"text":466,"correct":22},"1.05",{"key":27,"text":468,"correct":22},"0.95",{"key":31,"text":470,"correct":29},"0.9975",{"id":472,"libraryId":5,"type":15,"typeLabel":16,"stem":473,"options":474,"answer":24,"analysis":33},1118063,"适用于施工条件正常、产品稳定、统计工作制度健全的施工过程的人工定额的制定方法是（ ）。",[475,477,479,481],{"key":20,"text":476,"correct":22},"技术测定法",{"key":24,"text":478,"correct":29},"统计分析法",{"key":27,"text":480,"correct":22},"比较类推法",{"key":31,"text":482,"correct":22},"经验估计法",{"id":484,"libraryId":5,"type":15,"typeLabel":16,"stem":485,"options":486,"answer":20,"analysis":33},1118064,"编制预算定额的基础是（ ）。",[487,488,490,492],{"key":20,"text":265,"correct":29},{"key":24,"text":489,"correct":22},"时间定额",{"key":27,"text":491,"correct":22},"产量定额",{"key":31,"text":327,"correct":22},{"id":494,"libraryId":5,"type":15,"typeLabel":16,"stem":495,"options":496,"answer":20,"analysis":33},1118065,"时间定额与产量定额之间的关系为( )。",[497,499,501,503],{"key":20,"text":498,"correct":29},"互为倒数",{"key":24,"text":500,"correct":22},"互成正比",{"key":27,"text":502,"correct":22},"需分别独立测算",{"key":31,"text":504,"correct":22},"不存在直接关系",{"id":506,"libraryId":5,"type":15,"typeLabel":16,"stem":507,"options":508,"answer":20,"analysis":33},1118066,"关于预算定额，以下表述正确的是( )。",[509,511,513,515],{"key":20,"text":510,"correct":29},"预算定额是编制概算定额的基础",{"key":24,"text":512,"correct":22},"预算定额是以扩大的分部分项工程为对象编制的",{"key":27,"text":514,"correct":22},"预算定额是概算定额的扩大与合并",{"key":31,"text":516,"correct":22},"预算定额中人工工日消耗量的确定不考虑人工幅度差",{"id":518,"libraryId":5,"type":15,"typeLabel":16,"stem":519,"options":520,"answer":20,"analysis":33},1118067,"对于同类型产品规格多，工序重复、工作量小的施工过程，常用( )。",[521,522,523,524],{"key":20,"text":480,"correct":29},{"key":24,"text":482,"correct":22},{"key":27,"text":476,"correct":22},{"key":31,"text":478,"correct":22},{"id":526,"libraryId":5,"type":15,"typeLabel":16,"stem":527,"options":528,"answer":24,"analysis":33},1118068,"以建筑物或构筑物各个分部分项工程为对象编制的定额是()，以扩大的分部分项工程定额编制的是()。",[529,531,533,535],{"key":20,"text":530,"correct":22},"概算定额，预算定额",{"key":24,"text":532,"correct":29},"预算定额，概算定额",{"key":27,"text":534,"correct":22},"概算指标，概算定额",{"key":31,"text":536,"correct":22},"预算定额，投资估算指标",{"id":538,"libraryId":5,"type":15,"typeLabel":16,"stem":539,"options":540,"answer":24,"analysis":33},1118069,"关于周转性材料消耗量，下列说法正确的是()。",[541,543,545,547],{"key":20,"text":542,"correct":22},"周转性材料的消耗量是指材料使用量",{"key":24,"text":544,"correct":29},"周转性材料的消耗量应当用材料的一次使用量和摊销量两个指标表示",{"key":27,"text":546,"correct":22},"周转性材料的摊销量供施工企业组织使用",{"key":31,"text":370,"correct":22},{"id":549,"libraryId":5,"type":15,"typeLabel":16,"stem":550,"options":551,"answer":27,"analysis":33},1118070,"某工人小组在正常的施工条件下进行砖墙的砌筑，作业过程中所消耗的时间属于定额工作时间的是( )。",[552,554,556,558],{"key":20,"text":553,"correct":22},"工人对经检验不合格的部位重新砌筑使用的时间",{"key":24,"text":555,"correct":22},"砂浆没有按时运抵工作面而引起的停工时间",{"key":27,"text":557,"correct":29},"工人砌筑砖墙所消耗的时间",{"key":31,"text":559,"correct":22},"由于工地停电使砌筑施工无法进行所消耗的时间",{"id":561,"libraryId":5,"type":15,"typeLabel":16,"stem":562,"options":563,"answer":31,"analysis":33},1118071,"某施工机械纯工作每小时产量为20m3，机械利用系数为0.9，与之配合的工人小组4人，则该施工机械台班产量定额为()",[564,566,568,570],{"key":20,"text":565,"correct":22},"102m3／台班",{"key":24,"text":567,"correct":22},"120m3／台班",{"key":27,"text":569,"correct":22},"90m3／台班",{"key":31,"text":571,"correct":29},"144m3\u002F台班",{"id":573,"libraryId":5,"type":15,"typeLabel":16,"stem":574,"options":575,"answer":31,"analysis":33},1118072,"定额材料消耗指标的组成，按其使用性质、用途和用量大小划分不包括( )。",[576,578,580,582],{"key":20,"text":577,"correct":22},"主要材料，指直接构成工程实体的材料",{"key":24,"text":579,"correct":22},"辅助材料，也是直接构成工程实体，但比重较小的材料",{"key":27,"text":581,"correct":22},"零星材料，是指用量小，价值不大，不便计算的次要材料，可用估算法计算",{"key":31,"text":583,"correct":29},"特殊材料，是指用量不大，但价值很大的特殊材料",{"id":585,"libraryId":5,"type":15,"typeLabel":16,"stem":586,"options":587,"answer":27,"analysis":33},1118073,"按编制程序和用途分类，建设工程定额不包括( )。",[588,589,590,591],{"key":20,"text":265,"correct":22},{"key":24,"text":267,"correct":22},{"key":27,"text":291,"correct":29},{"key":31,"text":269,"correct":22},[593,596,599,602,605,608],{"id":15,"name":594,"category":7,"favorite":595},"领导干部任职前廉政法规知识测试题",92,{"id":597,"name":598,"category":7,"favorite":15},595,"建筑结构与设备",{"id":600,"name":601,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":603,"name":604,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":606,"name":607,"category":7,"favorite":8},534,"BIM工程师",{"id":609,"name":607,"category":7,"favorite":8},535]