[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120089":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1120089,789,1,"单选题","信息管理部门负责编制信息管理手册，在项目()进行信息管理手册的必要的修改和补充，并检查和督促其执行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实施过程中",true,{"key":16,"text":17,"correct":18},"B","可行性研究阶段",false,{"key":20,"text":21,"correct":18},"C","竣工验收时",{"key":23,"text":24,"correct":18},"D","开工时","2021\u002F2020教材P279页 “信息管理部门是专门从事信息管理的工作部门，其主要任务是：（1）负责主持编制信息管理手册，在项目实施过程中进行信息管理手册的必要的修改和补充，并检查和督促其执行。”",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]