[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120073":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1120073,789,1,"单选题","在大型建设工程项目中，因信息交流的问题导致工程变更和工程实施的错误约占工程总成本的（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3%～5%",true,{"key":16,"text":17,"correct":18},"B","4%～7%",false,{"key":20,"text":21,"correct":18},"C","5%～8%",{"key":23,"text":24,"correct":18},"D","8%～10%","2021\u002F2020教材P277页 ③在大型建设工程项目中，信息交流的问题导致工程变更和工程实施的错误约占工程总成本的3%--5%。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]