[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120061":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1120061,789,1,"单选题","建设工程项目的信息管理的目的旨在通过有效的项目信息传输的组织和控制为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建设的增值服务",true,{"key":16,"text":17,"correct":18},"B","项目目标控制服务",false,{"key":20,"text":21,"correct":18},"C","尽快发挥项目投资效益服务",{"key":23,"text":24,"correct":18},"D","提高项目管理效率服务","2021\u002F2020教材P276页 建设工程项目的信息管理的目的旨在通过有效的项目信息传输的组织和控制为项目建设提供增值服务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]