[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120026":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1120026,789,1,"单选题","施工单位应在完成施工测量方案、红线桩校核成果、水准点引测成果及施工过程的各种测量记录后，填写《施工测量放线报验表》报请()审核。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理单位",true,{"key":16,"text":17,"correct":18},"B","建设单位",false,{"key":20,"text":21,"correct":18},"C","设计单位",{"key":23,"text":24,"correct":18},"D","施工单位","2021\u002F2020教材P286页 施工测量放线报验表施工单位应在完成施工测量方案、红线桩校核成果、水准点引测成果及施工过程的各种测量记录后，填写《施工测量放线报验表》报请监理单位审核。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]