[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120024":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1120024,789,1,"单选题","某房建工程的给排水工程由项目专业技术负责人组织验收后，应由（）签署验收意见及验收结构，并签字盖章",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工企业施工员",false,{"key":16,"text":17,"correct":18},"B","专业监理工程师",true,{"key":20,"text":21,"correct":14},"C","项目专业技术负责人",{"key":23,"text":24,"correct":14},"D","建设单位参加验收的人员","2021\u002F2020教材P288页 （3）工程具备隐检条件后，由施工员填写隐蔽工程验收记录，由质检员提前一天报请监理单位，验收时由专业技术负责人组织施工员、质量检查员共同参加，验收后由监理单位专业监理工程师签署验收意见及验收结论，并签字签章。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]