[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1120020,789,1,"单选题","涉及结构形式、工艺、平面布置、项目等重大改变及图面变更面积超过()，应重新绘制竣工图。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":14},"B","30%",{"key":19,"text":20,"correct":21},"C","35%",true,{"key":23,"text":24,"correct":14},"D","40%","2021\u002F2020教材P290页 (5)涉及结构形式、工艺、平面布置、项目等重大改变及图面变更面积超过35%的，应重新绘制竣工图。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]