[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1120009,789,1,"单选题","施工单位在收齐工程文件整理立卷后，建设单位、监理单位应根据()的要求对档案文件完整、准确、系统情况和案卷质量进行审查。审查合格后向建设单位移交。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设主管部门",false,{"key":16,"text":17,"correct":14},"B","合同文件",{"key":19,"text":20,"correct":21},"C","城建档案管理机构",true,{"key":23,"text":24,"correct":14},"D","法律规范","2021\u002F2020教材P293页 “施工单位在收齐工程文件整理立卷后，建设单位、监理单位应根据城建档案管理机构的要求对档案文件完整、准确、系统情况和案卷质量进行审查。审查合格后向建设单位移交。”",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]