[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1120008":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1120008,789,1,"单选题","利用施工图改绘竣工图，必须标明变更修改依据；凡施工图结构、工艺、平面布置等有重大改变，或变更部分超过图面()的，应当重新绘制竣工图。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1\u002F2",false,{"key":16,"text":17,"correct":14},"B","1\u002F4",{"key":19,"text":20,"correct":14},"C","2\u002F3",{"key":22,"text":23,"correct":24},"D","1\u002F3",true,"2021\u002F2020教材P293页 “利用施工图改绘竣工图，必须标明变更修改依据；凡施工图结构、工艺、平面布置等有重大改变，或变更部分超过图面1\u002F3的，应当重新绘制竣工图。”",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]