[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119992":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119992,789,1,"单选题","工程施工质量验收资料不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工现场质量管理检查记录",false,{"key":16,"text":17,"correct":18},"B","隐蔽工程检查记录",true,{"key":20,"text":21,"correct":14},"C","分项工程质量验收记录",{"key":23,"text":24,"correct":14},"D","检验批质量验收记录","2021\u002F2020教材P289页 工程施工质量验收资料内容包括：1.施工现场质量管理检查记录；2.单位（子单位）工程质量竣工验收记录；3.分部（子分部）工程质量验收记录文件；4.分项工程质量验收记录文件；5.检验批质量验收记录文件。而B选项的隐蔽工程检查记录属于工程质量控制资料，并非是工程施工质量验收记录。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]