[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119990":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119990,789,1,"单选题","分项工程质量应由()组织项目专业技术负责人等进行验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","总监理工程师",{"key":19,"text":20,"correct":21},"C","专业监理工程师",true,{"key":23,"text":24,"correct":14},"D","监理员","2021\u002F2020教材P289页 分项工程完成（即分项工程所包含的检验批均已完工），施工单位自检合格后，应填报“————分项工程质量验收记录表”，由监理工程师（建设单位项目专业技术负责人）组织项目专业技术负责人进行验收并签认。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]