[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119974,789,1,"单选题","根据施工合同示范文本的规定，图纸会审和设计交底应由（）组织。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","承包人",{"key":23,"text":24,"correct":14},"D","设计单位","2021\u002F2020教材P285页 1.图纸会审记录文件图纸会审记录是对已正式签署的设计文件进行交底、审查和会审，对提出的问题予以记录的文件。项目经理部收到工程图纸后，应组织有关人员进行审查，将设计疑问及图纸存在的问题，按专业整理、汇总后报建设单位，由建设单位提交设计单位，进行图纸会审和设计交底准备。图纸会审由建设单位组织设计、监理、施工单位负责人及有关人员参加。设计单位对设计疑问及图纸存在的问题进行交底，施工单位负责将设计交底内容按专业汇总、整理，形成图纸会审记录。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]