[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119967,789,1,"单选题","关于工程档案的编制，下列表述中正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程档案应在竣工后及时收集整理",false,{"key":16,"text":17,"correct":18},"B","工程档案不得涂改和随意抽撤",true,{"key":20,"text":21,"correct":14},"C","工程档案的内容由建设单位确定",{"key":23,"text":24,"correct":14},"D","工程档案由施工单位组织编制","2021\u002F2020教材P284页 建设项目各参与方对于建设工程档案管理的通用职责如下：（1）工程各参建单位填写的工程档案应以工程合同、设计文件、工程质量验收标准、施工及验收规范等为依据；（2）工程档案应随工程进度及时收集、整理，并应按专业归类；（3）工程档案进行分级管理，各单位技术负责人负责本单位工程档案的全过程组织工作，工程档案的手机、整理和审核工作由各单位档案管理员负责；（4）对工程档案进行涂改、伪造、随意抽撤或损毁、丢失等，应按有关规定予以处罚。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]