[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119965":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119965,789,1,"单选题","平行发包给多个承包单位的建设工程项目，应由各承包单位负责收集、整理、立卷其承包项目的工程文件，并应当在工程竣工验收前及时向()移交。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","城建档案管理机构",{"key":23,"text":24,"correct":14},"D","质量监督机构","2021\u002F2020教材P284页 建设工程实行施工总承包的，由施工总承包单位负责收集、汇总各分包单位形成的工程档案，各分包单位应将本单位形成的工程文件整理、立卷后及时移交给总承包单位。建设工程项目由几个单位承包的，各承包单位负责收集、整理、立卷其承包项目的工程文件，并应当及时向建设单位移交，各承包单位应保证归档文件的完整、准确、系统，能够全面反映工程建设活动的全过程。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]