[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119964,789,1,"单选题","施工文件的归档范围详见《建设工程文件归档整理规范》的要求。对与工程建设有关的重要活动、记载工程建设（）、具有保存价值的各种载体文件，均应收集齐全，整理立卷后归档。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主要过程和现状",true,{"key":16,"text":17,"correct":18},"B","主要阶段和质量状况",false,{"key":20,"text":21,"correct":18},"C","安全和质量状况",{"key":23,"text":24,"correct":18},"D","进度与质量状况","2021\u002F2020教材P284页 2Z107021施工文件归档管理的内容在《建设工程文件归档规范》GB\u002FT50328-2014中明确建设工程档案是“在工程建设活动中直接形成的具有归档保存价值的文字、图表、声像等各种形式的历史记录，也可简称工程档案”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]