[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119961":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119961,789,1,"单选题","根据《建设工程施工劳务分包合同（示范文本）》（GF-2003-0214）规定，工程承包人收到劳务分包人递交的结算资料后()d内进行核实，给予确认或者提出修改意见。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","28","2021\u002F2020教材P248页 工程承包人收到劳务分包人递交的结算资料后14天内进行核实，给予确认或者提出修改意见。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]