[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119956,789,1,"单选题","采用( )方式的，施工过程中不计工时和工程量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","固定劳务报酬",true,{"key":16,"text":17,"correct":18},"B","按确定的工时计算劳务报酬的",false,{"key":20,"text":21,"correct":18},"C","按确认的工程量计劳务报酬的",{"key":23,"text":24,"correct":18},"D","计酬","2021\u002F2020教材P248页 1、采用固定劳务报酬方式的，施工过程中不计工时和工程量。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]