[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119954,789,1,"单选题","根据《建设工程施工劳务分包合同（示范文本）》(GF2003-0214)，全部分包工作完成，经工程承包人认可后（）日内，劳务分包人向工程承包人递交完整的结算资料，按照合同约定进行劳务报酬的最终支付。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","42","2021\u002F2020教材P248页 全部工作完成，经工程承包人认可后14天内，劳务分包人向工程承包人递交完整的结算资料，双方按照本合同约定的计价方式，进行劳务报酬的最终支付。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]