[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119952,789,1,"单选题","甲公司是某建设项目的施工总承包管理单位，乙公司是该项目的分包单位，则下述表述中正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","一般情况下，乙公司的分包合同应与甲公司签订",false,{"key":16,"text":17,"correct":14},"B","甲公司负责分包合同的管理与协调工作，对项目目标控制不承担责任",{"key":19,"text":20,"correct":14},"C","如甲公司认为乙公司没有能力完成分包任务，但业主不同意更换，则甲公司应认可该分包合同",{"key":22,"text":23,"correct":24},"D","甲公司只收取总包管理费，不赚总包与分包之间的差价",true,"2021\u002F2020教材P226页 (3)施工总承包管理单位只收取总包管理费，不赚总包与分包之间的差价",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]