[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119947":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119947,789,1,"单选题","某工程项目施工过程中，先后发生了多次暂停施工：①由于监理人未能按约定提供图纸，导致暂停施工5天；②由于承包人已完工程出现质量问题，监理人要求进行质量整改，导致暂停施工8天；③由于发包人未能按合同约定支付工程款，导致暂停施工10天；④由于达到专用条件规定的异常恶劣气候条件的暴雨，导致暂停施工4天。根据《标准施工招标文件》中“通用合同条款”的规定，对上述情况导致的暂停施工，承包人可获得的工期顺延为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","13天",false,{"key":16,"text":17,"correct":14},"B","15天",{"key":19,"text":20,"correct":21},"C","19天",true,{"key":23,"text":24,"correct":14},"D","27天","2021\u002F2020教材P237页 (1)承包人暂停施工的责任因下列暂停施工增加的费用和（或）工期延误由承包人承担：①承包人违约引起的暂停施工；②由于承包人原因为工程合理施工和安全保障所必需的暂停施工；③承包人擅自暂停施工；④承包人其他原因引起的暂停施工；⑤专用合同条款约定由承包人承担的其他暂停施工。(2)发包人暂停施工的责任由于发包人原因引起的暂停施工造成工期延误的，承包人有权要求发包人延长工期和(或）增加费用，并支付合理利润。①属于监理方的过错，②属于施工方的过错，③属于发包方的过错，④属于不可抗力的因素，所以能顺延的为①③④，19天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]