[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119946,789,1,"单选题","监理人发出暂停施工指示后()d内未向承包人发出复工通知，除了该项停工属于承包人暂停施工的责任的情况外，承包人可向监理人提交书面通知，要求监理人在收到书面通知后28d内准许已经暂停施工的工程或其中一部分工程继续施工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","28",{"key":19,"text":20,"correct":21},"C","56",true,{"key":23,"text":24,"correct":14},"D","90","2021\u002F2020教材P238页 （5）暂停施工持续56天以上：监理人发出暂停施工指示后56天内未向承包人发出复工通知，除了该项停工属于第12.1款（即由于承包人暂停施工的责任）的情况外，承包人可向监理人提交书面通知，要求监理人在收到书面通知后28天内准许已暂停施工的工程或其中一部分工程继续施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]