[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119945,789,1,"单选题","如果招标人在招标文件已经发布之后，发现有问题需要进一步的澄清或修改，应当在招标文件要求提交投标文件截止时间至少()日前发出。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","15",true,{"key":23,"text":24,"correct":14},"D","30","2021\u002F2020教材P228页 2.招标信息的修正（1）时限：招标人对已发出的招标文件进行必要的澄清或者修改，应当在招标文件要求提交投标文件截止时间至少15日前发出。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]