[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119941,789,1,"单选题","如发包人提供的测量基准点错误导致工程损失，发包人应()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承担由此增加的费用，但不承担工期延误",false,{"key":16,"text":17,"correct":14},"B","承担由此造成的工期延误，但不承担由此增加的费用",{"key":19,"text":20,"correct":14},"C","承担由此增加的费用和工期延误，但不补偿承包人利润损失",{"key":22,"text":23,"correct":24},"D","承担由此增加的费用和工期延误，并向承包人支付合理利润",true,"2021\u002F2020教材P234页 发包人应对其提供的测量基准点、基准线和水准点及其书面资料的真实性、准确性和完整性负责。发包人提供上述基准资料错误导致承包人测量放线工作的返工或造成工程损失的，发包人应当承担由此增加的费用和（或）工期延误，并向承包人支付合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]