[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119938,789,1,"单选题","某工程项目承包人按合同要求向监理人提交了工程进度计划，并根据监理人的意见对工程进度计划进行了修改，监理人对修改后的工程进度计划予以确认。在施工过程中，发现由于进度计划安排不善导致出现了人员窝工的情况，由此产生的后果应由()承担。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":14},"C","发包人与承包人共同",{"key":22,"text":23,"correct":24},"D","承包人",true,"2021\u002F2020教材P237页 由于承包人原因，未能按合同进度计划完成工作，或监理人认为承包人施工进度不能满足合同工期要求的，承包人应采取措施加快进度，并承担加快进度所增加的费用。施工进度安排不当，属于施工方的过错，进度计划本身并不存在问题",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]