[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119935":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119935,789,1,"单选题","根据《标准施工招标文件》，除专用合同条款另有约定外，经验收合格工程的实际竣工日期，以()的日期为准，并在工程接收证书中写明。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人实际完成工程的日期",false,{"key":16,"text":17,"correct":14},"B","工程竣工验收后，发包人给予认可意见的日期",{"key":19,"text":20,"correct":14},"C","组织工程竣工验收的日期",{"key":22,"text":23,"correct":24},"D","提交竣工验收申请报告的日期",true,"2021\u002F2020教材P242页 (5)除专用合同条款另有约定外，经验收合格工程的实际竣工日期，以提交竣工验收申请报告的日期为准，并在工程接收证书中写明。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]