[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119933":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119933,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，监理人出具进度付款证书，则()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","视为监理人已同意承包人完成的该部分工作",false,{"key":16,"text":17,"correct":14},"B","视为发包人已接受承包人完成的该部分工作",{"key":19,"text":20,"correct":14},"C","发包人应在收到该证书后28天内，将进度款支付给承包人",{"key":22,"text":23,"correct":24},"D","不应视为监理人已批准了承包人完成的该部分工作",true,"2021\u002F2020教材P240页 监理人出具进度付款证书，不应视为监理人已同意、批准或接受了承包人完成的该部分工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]