[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119932":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119932,789,1,"单选题","承包人按照专用合同条款的规定份数和期限向监理人提交竣工付款申请单的时间是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程接受证书颁发前",false,{"key":16,"text":17,"correct":18},"B","工程接受证书颁发后",true,{"key":20,"text":21,"correct":14},"C","缺陷责任期终止证书颁发前",{"key":23,"text":24,"correct":14},"D","缺陷责任期终止证书颁发后","2021\u002F2020教材P241页 工程接收证书颁发后，承包人应按专用合同条款约定的份数和期限向监理人提交竣工付款申请单，并提供相关证明材料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]