[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119925,789,1,"单选题","采用固定总价合同形式发包工程，承包商为了降低自己在工程量和价格上承担的风险，通常会在合同报价中报较高的( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施费",false,{"key":16,"text":17,"correct":18},"B","不可预见风险费",true,{"key":20,"text":21,"correct":14},"C","单价",{"key":23,"text":24,"correct":14},"D","管理费","2021\u002F2020教材P254页 “采用固定总价合同，双方结算比较简单，但是由于承包商承担了较大的风险，因此报价中不可避免地要增加一笔较高的不可预见风险费。”",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]