[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119921,789,1,"单选题","设备采购合同通常采用()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可调单价合同",false,{"key":16,"text":17,"correct":18},"B","固定总价合同",true,{"key":20,"text":21,"correct":14},"C","可调总价合同",{"key":23,"text":24,"correct":14},"D","成本加酬金合同","2021\u002F2020教材P251页 设备采购合同通常采用固定总价合同，在合同交货期内价格不进行调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]