[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119919,789,1,"单选题","某施工工程发包时工程量不明确，因此采用单价合同，并根据估算的总工程量约一个合同总价。在实际结算时，上述合同总价与合同各项单价乘以实际完成工程量之和不一致，则应付工程款应以（）为准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","签订的合同总价",false,{"key":16,"text":17,"correct":18},"B","合同中各项单位乘以实际完成的工程量之和：成的工程量之和",true,{"key":20,"text":21,"correct":14},"C","实际完成的工程量乘以重新协商的各项单价之和",{"key":23,"text":24,"correct":14},"D","双方重新协商确定的单价和工程量","2021\u002F2020教材P252页 当发包工程的内容和工程量一时尚不能明确、具体地予以规定时，则可以采用单价合同形式，即根据计划工程内容和估算工程量，在合同中明确每项工程内容的单位价格（如每米、每平方米或者每立方米的价格），实际支付时则根据实际完成的工程量乘以合同单价计算应付工程款。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]