[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119917,789,1,"单选题","某建设工程项目承包合同的计价方式是单价合同，地基与基础分部工程完成后，其钢筋混凝土工程实际完成的工程量是2007立方米，而投标时工程量清单中该分项的工程量是1995立方米。在这种情况下，业主应根据()算该分项应付的工程款。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1995立方米乘以合同单价",false,{"key":16,"text":17,"correct":14},"B","1995立方米乘以调整后的单价",{"key":19,"text":20,"correct":21},"C","2007立方米乘以合同单价",true,{"key":23,"text":24,"correct":14},"D","2007立方米乘以调整后的单价","2021\u002F2020教材P253页 “在工程实践中，采用单价合同有时也会根据估算的工程量计算一个初步的合同总价，作为投标报价和签订合同之用。当合同总价与各项单价乘以实际完成的工程量之和发生矛盾时，则以后者为准，即单价优先。实际工程款的支付也将以实际完成工程量乘以合同单价进行计算。”",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]