[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119910":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119910,789,1,"单选题","在招标时，当图纸、规范准备不充分，不能据以确定合同价格，而仅能制订一个估算指标时，宜采用（）合同。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本加固定费用",false,{"key":16,"text":17,"correct":14},"B","成本加固定比例费用",{"key":19,"text":20,"correct":21},"C","成本加奖金",true,{"key":23,"text":24,"correct":14},"D","最大成本加费用","2021\u002F2020教材P256页 在招标时，当图纸、规范等准备不充分，不能据以确定合同价格，而仅能制定一个估算指标时可以采用成本加奖金的合同形式。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]