[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119908":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119908,789,1,"单选题","根据《标准施工招标文件》,下列不属于工程变更范围的是(",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","改变合同中任何一项工作的质量或其他特性",false,{"key":16,"text":17,"correct":18},"B","取消合同中任何一项工作,被取消的工作转由其他人实施",true,{"key":20,"text":21,"correct":14},"C","改变合同工程的基线、标高、位置或尺寸",{"key":23,"text":24,"correct":14},"D","为完成工程需要追加的额外工作","2021\u002F2020教材P259页 按《标准施工招标文件》规定进行变更的情况: (1)取消合同中任何一项工作,但被取消的工作不能转由发包人或其他人实施； (2)改变合同中任何一项工作的质量或其他特性； (3)改变合同工程的基线、标高、位置或尺寸； (4)改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序； (5)为完成工程需要追加的额外工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]