[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119901,789,1,"单选题","施工承包合同索赔成立的条件之一是：造成承包人费用增加或工期损失的原因，按合同约定()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不属于发包人的合同责任或风险责任",false,{"key":16,"text":17,"correct":18},"B","不属于承包人的行为责任或风险责任",true,{"key":20,"text":21,"correct":14},"C","属于承包人的可预见的不利外界条件",{"key":23,"text":24,"correct":14},"D","属于分包人的风险","2021\u002F2020教材P262页 索赔的成立，应该同时具备三个前提条件：（1）与合同对照，事件已造成了承包人工程项目成本的额外支出，或直接工期损失；（2）造成费用增加或工期损失的原因，按合同约定不属于承包人的行为责任或风险责任；（3）承包人按合同规定的程序和时间提交索赔意向通知和索赔报告。以上三个条件必须同时具备，缺一不可。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]