[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119898,789,1,"单选题","承包人必须在发出索赔意向通知后的( )天内，提交一份详细的索赔文件和有关资料。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7天",false,{"key":16,"text":17,"correct":14},"B","14天",{"key":19,"text":20,"correct":14},"C","21天",{"key":22,"text":23,"correct":24},"D","28天",true,"2021\u002F2020教材P264页 承包人必须在发出索赔意向通知后28天内或经过工程师（监理人）同意的其他合理时间内向工程师（监理人）提交一份详细的索赔文件和有关资料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]