[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119895":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119895,789,1,"单选题","根据《建设工程施工专业分包合同（示范文本）》规定，承包人应当向分包人提供（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","全套总包合同供分包人查阅",false,{"key":16,"text":17,"correct":14},"B","合同专用条款中约定的设备和设施，费用由分包人承担",{"key":19,"text":20,"correct":14},"C","与监理公司签订的合同",{"key":22,"text":23,"correct":24},"D","与分包工程相关的各种证件、批件和各种相关资料",true,"2021\u002F2020教材P244页 承包人的工作向分包人提供与分包工程相关的各种证件、批件和各种相关资料，向分包人提供具备施工条件的施工场地。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]