[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119894":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119894,789,1,"单选题","根据专业工程分包合同示范文本规定，分包合同约定的工程变更调整的合同价款，应()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","与工程结算款同期支付",false,{"key":16,"text":17,"correct":18},"B","与工程进度款同期调整支付",true,{"key":20,"text":21,"correct":14},"C","单独支付",{"key":23,"text":24,"correct":14},"D","以上三种方式均可","2021\u002F2020教材P246页 分包合同约定的工程变更调整的合同价款、合同价款的调整、索赔的价款或费用以及其他约定的追加合同价款，应与工程进度款同期调整支付。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]