[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119889,789,1,"单选题","某开发公司在工程建设方面经验不足，目前拟建项目的施工图设计尚未完成，在此情况下，为早日开工，该公司可采用的较为适宜的承发包模式是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","平行承发包",false,{"key":16,"text":17,"correct":14},"B","施工总承包",{"key":19,"text":20,"correct":21},"C","施工总承包管理",true,{"key":23,"text":24,"correct":14},"D","分别承发包","2021\u002F2020教材P224页 而如果采用施工总承包管理模式，对施工总承包管理单位的招标可以不依赖完整的施工图，施工总承包管理模式的招投标可以提前到项目尚处于设计阶段进",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]