[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119886,789,1,"单选题","不属于施工平行承发包模式中进度控制内容的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","某一部分施工图完成后，即可开始这部分工程的招标，开工日期提前，可以边设计边施工，缩短建设周期",false,{"key":16,"text":17,"correct":18},"B","一般要等施工图设计全部结束后，才能进行施工总承包单位的招标，开工日期较迟，建设周期势必较长，对进度控制不利",true,{"key":20,"text":21,"correct":14},"C","工程总进度计划和控制由业主负责",{"key":23,"text":24,"correct":14},"D","由于要进行多次招标，业主用于招标的时间较多","2021\u002F2020教材P222页 施工平行承发包的特点：1.某一部分施工图完成后，即可开始这部分工程的招标，开工日期提前，可以边设计边施工，缩短建设周期；2.由于要进行多次招标，业主用于招标的时间较多；3.施工总进度计划和控制由业主负责。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]