[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119885,789,1,"单选题","建设工程施工施工总承包模式的最大缺点是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设周期较短",false,{"key":16,"text":17,"correct":14},"B","合同管理工作量大",{"key":19,"text":20,"correct":14},"C","业主对总承包施工单位的依赖较大",{"key":22,"text":23,"correct":24},"D","对进度控制不利",true,"2021\u002F2020教材P223页 2.进度控制。(1)一般要等施工图设计全部结束后，才能进行施工总承包的招标，开工日期较迟，建设周期势必较长，对项目总进度控制不利。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]