[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119882,789,1,"单选题","以下关于施工平行发承包模式的特点，说法错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对某些工作而言，符合质量控制上的“他人控制”原则",false,{"key":16,"text":17,"correct":18},"B","需全部施工图完成后才进行招标，对进度控制不利",true,{"key":20,"text":21,"correct":14},"C","业主要负责所有施工承包合同的招标、合同谈判、签约，招标工作量大，对业主不利",{"key":23,"text":24,"correct":14},"D","业主直接控制所有工程的发包，可决定所有工程的承包商的选择","2021\u002F2020教材P222页 (1)某一部分施工图完成后，即可开始这部分工程的招标，开工日期提前，可以边设计边施工，缩短建设周期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]