[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119876,789,1,"单选题","下列选项中，不属于索赔资料准备阶段的主要工作的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","跟踪和调查干扰事件",false,{"key":16,"text":17,"correct":14},"B","分析干扰事件产生的原因，划清各方责任，确定索赔根据",{"key":19,"text":20,"correct":21},"C","确定索赔对象，明确索赔的项目",true,{"key":23,"text":24,"correct":14},"D","收集证据，获得充分而有效的各种证据","2021\u002F2020教材P264页 1.在索赔资料准备阶段，主要工作有：（1）跟踪和调查干扰事件，掌握事件产生的详细经过；（2）分析干扰事件产生的原因，划清各方责任，确定索赔根据；（3）损失或损害调查分析与计算，确定工期索赔和费用索赔值；（4）收集证据，获得充分而有效的各种证据；（5）起草索赔文件（索赔报告）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]