[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119870":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119870,789,1,"单选题","监理人在收到承包人索赔通知书或有关索赔的进一步证明资料后的()内，将索赔处理结果答复给承包人",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","28天",false,{"key":16,"text":17,"correct":14},"B","14天",{"key":19,"text":20,"correct":21},"C","42天",true,{"key":23,"text":24,"correct":14},"D","56天","2021\u002F2020教材P265页 (2)监理人应按第3.5款商定或确定追加的付款和（或）延长的工期，并在收到上述索赔通知书或有关索赔的进一步证明材料后的42天内，将索赔处理结果答复承包人。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]