[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119869,789,1,"单选题","根据《标准施工招标文件》，承包人按合同约定提交的最终结清申请单中，只限于提出工程接收证书颁发后发生的索赔。提出索赔的期限自接受()时终止。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竣工付款证书",false,{"key":16,"text":17,"correct":14},"B","工程验收证书",{"key":19,"text":20,"correct":21},"C","最终结清证书",true,{"key":23,"text":24,"correct":14},"D","临时付款证书","2021\u002F2020教材P265页 (2)承包人按合同约定提交的最终结清申请单中，只限于提出工程接收证书颁发后发生的索赔。提出索赔的期限自接受最终结清证书时终止。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]