[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119867,789,1,"单选题","为了不失去索赔权利，承包人应在干扰事件影响结束后的()天内，提交最终索赔报告。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","21",{"key":22,"text":23,"correct":24},"D","28",true,"2021\u002F2020教材P264页 如果干扰事件对工程的影响持续时间长，承包人则应按工程师（监理人）要求的合理间隔（一般为28天），提交中间索赔报告，并在干扰事件影响结束后的28天提交一份最终索赔报告。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]