[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119863,789,1,"单选题","索赔事件（又称为干扰事件）使实际情况与合同规定不符合，其在施工过程中最终引起的应是()的变化。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","规范和标准",false,{"key":16,"text":17,"correct":14},"B","方案和部署",{"key":19,"text":20,"correct":14},"C","合同条件",{"key":22,"text":23,"correct":24},"D","工期和费用",true,"2021\u002F2020教材P262页 索赔事件，又称为干扰事件，是指那些使实际情况与合同规定不符合，最终引起工期和费用变化的各类事件。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]