[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119859":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119859,789,1,"单选题","某新校区抗震模拟实验室工程，模拟振动台设备基础采用钢筋混凝土大块基础，混凝土施工要求使用商品混凝土。但在模拟振动台设备基础施工中，由于业主要求从使用商品混凝土变更为现场搅拌，致使工程延期3天。则承包商可索赔材料费的情况是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工价格上涨",false,{"key":16,"text":17,"correct":18},"B","材料超期储存",true,{"key":20,"text":21,"correct":14},"C","材料被盗和损坏",{"key":23,"text":24,"correct":14},"D","材料进货日期变化","2021\u002F2020教材P262页 索赔成立的条件：（2）因工程变更（含设计变更、发包人提出的工程变更、监理工程师提出的工程变更，以及承包人提出并经监理工程师批准的变更）造成的时间、费用损失。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]